Mine Dewatering – High Pressure Conditions

Water line feed from wells to mine

Case Study Nº

6

Customer

Antofagasta Minerals, Michilla Mine
Chile

|

2011

Working Conditions

High pressure (over 24 bar).

Pexgol Pipes

Pexgol 160×27, Class 30.

Application

Dewatering.

Lenght

700 meters.

Categories

Mine Dewatering – High Pressure Conditions

The Challenge

Antofagasta Minerals faced constant water accumulation at the bottom of the mine, it was interfering with the extraction of the minerals. In addition, the mine operators faced:

  • High pressure (more than 24 bars) – resulting from the vertical height differences, which required a pipe that could withstand the pressure and be easily installed.
  • Pipe clogging in HDPE pipes – caused by scale formation on the pipe walls due to the presence of various salts, such as chlorides and sulfates, in varying concentrations in the water.
  • Long installation time – and the need to reduce it by installing a flexible, long pipeline with less connections.

Pexgol Solution

The installation of a Pexgol’s flexible pipe, which was produced and transported in coils, reducing both installation time as well as the number of joints. Since installation in early 2011, it has been working with no sign of clogging.

The client is fully satisfied with the pipe’s robust performance, including its quick, easy installation and ability to withstand pressures of higher than 24 bars.

Since Pexgol’s pipes require less maintenance than PE pipes and eliminate previous frequent failures, it will be used for many additional applications at the mine.

Related Case Studies

Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023