Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Case Study Nº

177

Customer

Kimex
Mexico

|

2025

Working Conditions

Temperature: 16°C – 31°C (Ambient) | Pressure: 3 bar | Flow Rate: 115 m³/hr | Fluid: Boiler feedwater

Pexgol Pipes

Pexgol 4″ SDR 11

Application

Water conveyance for power plant commissioning

Lenght

600 m / 1968 ft

Categories

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

The Challenge

Kiewit Corp., through its subsidiary Kimex SA de CV, faced a critical requirement during the construction of the CCC Tuxpan Phase 1 combined-cycle power plant in Mexico. To initiate testing and commissioning, the new facility needed to be supplied with boiler feedwater—a fluid requiring high purity and specific properties.

The challenge: the site under construction lacked an operational water treatment system, and any solution had to be immediate, highly reliable, and compatible with Kiewit’s rigorous safety protocols. Additionally, the piping had to withstand conditions typical of an active construction environment.

The Solution

Pexgol proved to be the ideal choice. In just one day, 600 meters of 4” SDR 11 Pexgol pipe were installed using only standard on-site machinery and tools, with no need for specialized equipment. The very next day, the system was operational, enabling the project team to start equipment testing without delay.

The line transported boiler feedwater at 3 bar of pressure and a flow rate of 115 m³/h, operating smoothly within the site’s ambient temperature range of 16°C to 31°C.

A key success factor was Kiewit’s validation of internal safety protocols. Although using coiled piping was new to their team, the installation was incident-free, demonstrating Pexgol’s safety and reliability even in demanding construction environments.

Key Benefits:

  • Rapid installation without specialized equipment
  • Flexible and impact-resistant material, ideal for active worksites
  • Excellent chemical and corrosion resistance
  • Lightweight and easy to handle
  • Full compliance with international safety protocols

Fittings Used:

  • Flared End / Stub End
  • Loose Flange
  • Fixpoint Bridge

Related Case Studies

Transportation of River Water in Rough Terrain

Water Transport in Complex Terrain

Southern Copper Corporation
Peru

 | 

2019
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Innovation and improvement in fluid transportation in the oil and gas industry.

Streamlining Effluent Treatment with Pexgol

Pan American Energy
Argentina

 | 

2023
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016