Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Case Study Nº

177

Customer

Kimex
Mexico

|

2025

Working Conditions

Temperature: 16°C – 31°C (Ambient) | Pressure: 3 bar | Flow Rate: 115 m³/hr | Fluid: Boiler feedwater

Pexgol Pipes

Pexgol 4″ SDR 11

Application

Water conveyance for power plant commissioning

Lenght

600 m / 1968 ft

Categories

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

The Challenge

Kiewit Corp., through its subsidiary Kimex SA de CV, faced a critical requirement during the construction of the CCC Tuxpan Phase 1 combined-cycle power plant in Mexico. To initiate testing and commissioning, the new facility needed to be supplied with boiler feedwater—a fluid requiring high purity and specific properties.

The challenge: the site under construction lacked an operational water treatment system, and any solution had to be immediate, highly reliable, and compatible with Kiewit’s rigorous safety protocols. Additionally, the piping had to withstand conditions typical of an active construction environment.

The Solution

Pexgol proved to be the ideal choice. In just one day, 600 meters of 4” SDR 11 Pexgol pipe were installed using only standard on-site machinery and tools, with no need for specialized equipment. The very next day, the system was operational, enabling the project team to start equipment testing without delay.

The line transported boiler feedwater at 3 bar of pressure and a flow rate of 115 m³/h, operating smoothly within the site’s ambient temperature range of 16°C to 31°C.

A key success factor was Kiewit’s validation of internal safety protocols. Although using coiled piping was new to their team, the installation was incident-free, demonstrating Pexgol’s safety and reliability even in demanding construction environments.

Key Benefits:

  • Rapid installation without specialized equipment
  • Flexible and impact-resistant material, ideal for active worksites
  • Excellent chemical and corrosion resistance
  • Lightweight and easy to handle
  • Full compliance with international safety protocols

Fittings Used:

  • Flared End / Stub End
  • Loose Flange
  • Fixpoint Bridge

Related Case Studies

Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016