Skip to content

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Reducing maintenance and increasing safety in hydraulic backfill operations.

Case Study Nº

166

Customer

Zijin – Continental Gold
Colombia

|

2023

Working Conditions

Temperature: 25°C / 77°F | Pressure: 8 bar | Fluid Components: Sand, water, cement (70% solids)

Pexgol Pipes

Pexgol 160 mm, class 15

Application

Slurry transport for hydraulic backfill

Lenght

70 m / 229.65 ft

Categories

Pexgol Simplifies Slurry Transportation at Buriticá Mine

The Challenge

Zijin-Continental Gold, operator of the Buriticá Mine in Colombia, faced a significant challenge in transporting slurry for hydraulic backfill—a complex application due to the abrasive and scaling nature of the fluid, composed of sand, cement, and water.

The previously used HDPE pipes suffered from wear, leakage at connections, and installation difficulties in the underground environment, characterized by limited space, lack of lighting, and scarce resources. A more durable and efficient solution was clearly needed, especially in the section between levels 1140 and 1105, where the velocity on
the slope increased wear on the pipes.

The Solution

To tackle these issues, 160 mm, class 15 Pexgol pipes were installed in a section of the project. Pexgol was selected for its high abrasion resistance and because it is supplied in coils of up to 600 meters, ensuring safe and efficient
installation. The installation was completed over two shifts: during the first shift, the pipe was uncoiled, and in the second shift, it was lowered through the ventilation shaft, with the support system placed at the back of the setup, and transition joints between steel and Pexgol made using flanged couplings.

The implementation of Pexgol pipes at the Buriticá Mine resulted in a quick and efficient installation, eliminating the wear and leakage issues that affected the HDPE pipes. The flexibility of the material allowed for easy adaptation to the underground conditions, with supports required only every 3 meters in the horizontal section and no need for supports in the vertical section. This solution not only improved the durability and efficiency of the slurry transport system but also significantly reduced maintenance costs and enhanced operational safety.

This collaboration highlights how technological solutions can transform mining operations, improving both productivity and safety.

Related Case Studies

Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015