Skip to content

Pumping Mining Effluents

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Case Study Nº

88

Customer

AngloGold Ashanti
Brazil

|

2019

Working Conditions

Temperature: 30°C / 86°F | Pressure: 12 bar | Flow: 150 m³/h

Pexgol Pipes

Pexgol 225 mm (8”), Class 24

Application

Dewatering

Lenght

120 m / 393.70 ft

Categories

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

The Challenge

AngloGold had urgency in installing a new pumping line to remove effluents from the mine. Using traditional pipes could take up to two months to get the job done, considering all the preparation required to install such pipes. Furthermore, for AngloGold, using regular piping would mean putting its people in danger during the preparation to install the pipes and during installation itself.

Pexgol Solution

Using Pexgol allowed AngloGold to reduce the installation time by ten times, as a single continuous 120-meter-long pipe was used. Through an existing hole drilled on the mine the pipe was descended connecting its upper and lower parts. There was no need for people to be kept hanging at high heights to prepare any kind of structure to install the pipeline and no joints aside from the two extremes of the pipe were needed.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

It was an easy installation process, despite being the first time using Pexgol, and it was all done by AngloGold’s crew itself.
With a Volvo L90 loader and a JCB Loadall telescopic handler the crew completed the installation in 3 days

Related Case Studies

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Carriage of Chemicals at Sea Port

Ashdod Sea Port
Israel

 | 

2016
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023