Pumping Mining Effluents

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Case Study Nº

88

Customer

AngloGold Ashanti
Brazil

|

2019

Working Conditions

Temperature: 30°C / 86°F | Pressure: 12 bar | Flow: 150 m³/h

Pexgol Pipes

Pexgol 225 mm (8”), Class 24

Application

Dewatering

Lenght

120 m / 393.70 ft

Categories

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

The Challenge

AngloGold had urgency in installing a new pumping line to remove effluents from the mine. Using traditional pipes could take up to two months to get the job done, considering all the preparation required to install such pipes. Furthermore, for AngloGold, using regular piping would mean putting its people in danger during the preparation to install the pipes and during installation itself.

Pexgol Solution

Using Pexgol allowed AngloGold to reduce the installation time by ten times, as a single continuous 120-meter-long pipe was used. Through an existing hole drilled on the mine the pipe was descended connecting its upper and lower parts. There was no need for people to be kept hanging at high heights to prepare any kind of structure to install the pipeline and no joints aside from the two extremes of the pipe were needed.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

It was an easy installation process, despite being the first time using Pexgol, and it was all done by AngloGold’s crew itself.
With a Volvo L90 loader and a JCB Loadall telescopic handler the crew completed the installation in 3 days

Related Case Studies

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Carriage of Chemicals at Sea Port

Ashdod Sea Port
Israel

 | 

2016
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

Comparison of brine transport

Albemarle Salar
Chile

 | 

2020
A Two-Phase Installation for High-Temperature Hot Water Supply & Return.

Scaling Up Efficiency: District Energy at Penn State Harrisburg

Penn State University - Harrisburg
USA

 | 

2021