Slurry Transportation

Replacement of a HDPE Pipe for a Pexgol Pipe

Case Study Nº

40

Customer

Sabinas Mine
Mexico

|

2017

Working Conditions

Discharge by gravity, ambient temperature, abrasive fluid.

Pexgol Pipes

Pexgol SDR 15 225 x 20.4.

Application

Slurry transportation.

Lenght

1642 meters.

Categories

Replacement of a HDPE Pipe for a Pexgol Pipe

The Challenge

The client required to replace their current HDPE pipe lines where they transported slurry since they have frequent wear and leak issues on the joints. They used thermo-fusion welding, plus reinforcement with a Vitaulic 995 coupler. This sort of situation involved a considerable expense every time they failed, but they didn’t last long. The failures were every 3 to 4 months.

Pexgol Solution

In order to perform a better job when transporting slurry, the client decided to install a Pexgol pipe of 1642 meters SDR 15 225 x 20.4.

Thanks to Pexgol’s comprehensive piping solution, abrasion issues were avoided, since its cross-linked material is between 4 to 10 times more resistant than other pipes materials.

The pipes were supplied n sections up to 240 meters each one, consequently the installation was simple improving the process’s security and therefore protecting the environment.

Related Case Studies

Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011
Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023