Skip to content

Slurry Transportation

Replacement of a HDPE Pipe for a Pexgol Pipe

Case Study Nº

40

Customer

Sabinas Mine
Mexico

|

2017

Working Conditions

Discharge by gravity, ambient temperature, abrasive fluid.

Pexgol Pipes

Pexgol SDR 15 225 x 20.4.

Application

Slurry transportation.

Lenght

1642 meters.

Categories

Replacement of a HDPE Pipe for a Pexgol Pipe

The Challenge

The client required to replace their current HDPE pipe lines where they transported slurry since they have frequent wear and leak issues on the joints. They used thermo-fusion welding, plus reinforcement with a Vitaulic 995 coupler. This sort of situation involved a considerable expense every time they failed, but they didn’t last long. The failures were every 3 to 4 months.

Pexgol Solution

In order to perform a better job when transporting slurry, the client decided to install a Pexgol pipe of 1642 meters SDR 15 225 x 20.4.

Thanks to Pexgol’s comprehensive piping solution, abrasion issues were avoided, since its cross-linked material is between 4 to 10 times more resistant than other pipes materials.

The pipes were supplied n sections up to 240 meters each one, consequently the installation was simple improving the process’s security and therefore protecting the environment.

Related Case Studies

Sewage Water Transportation with 300 PPM Hydrogen Peroxide

Sewage Water Transportation

BorsodChem
Hungary

 | 

2011
Replacement Of PVC Piping for PE-X in a Industrial Heating System.

Transport of Hot Air for Advanced Agriculture

Teva Post
Israel

 | 

2022
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016