Skip to content

Transport of Cyanide Water

Pexgol Pipe Installation for the Transport of Cyanide Water.

Case Study Nº

112

Customer

Equinox Gold
Mexico

|

2022

Working Conditions

Fluid: Neutralized Solution pH 10-12 – cyanide water | Flow: 1000m3/hr | Suction level: 1352 m3/hr | Discharge level: 1431/1432 m3/hr

Pexgol Pipes

Pexgol 400 mm (16”), class 10 & 15

Application

Transport of cyanide water

Lenght

1475 m / 4839 ft

Categories

Pexgol Pipe Installation for the Transport of Cyanide Water.

The Challenge

Equinox Gold, a Canadian mining company dedicated to gold extraction in different countries, required for its “Los Filos” mining unit to pump from the ADR plant a neutralized solution (cyaninated water) for evaporation through sprinklers. Previously, steel and HDPE pipes were used for this type of application.

The steel suffered from corrosion problems and the HDPE from crystallization, which generated problems in the thermofusions.

Pexgol Solution

It was decided to use Pexgol in sections of 12 meters with electrofusion connections. This way, possible corrosion problems were avoided and the costs of the project were reduced.

The installation was carried out by the same personnel working at the mine with training from the Pexgol technical team.

Related Case Studies

Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017
Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024