Skip to content

Water transport in textile factory

Water Transport from a Borehole with Low Ph.

Case Study Nº

59

Customer

CMT La Laguna
Mexico

|

2018

Working Conditions

Pressure 4.5 bar, temperature at 40°C

Pexgol Pipes

Pexgol 160 mm (6”), Class 15; Pexgol 225 mm (8”) Class 15

Application

Water transport

Lenght

2000 m

Categories

Water Transport from a Borehole with Low Ph.

The Challenge

The company CMT La Laguna is a jeans textile factory (Levis brand), which due to its economic growth, saw the need to expand its factory, which led to an increase in processes and as a consequence greater water usage in the manufacturing process.

For the installation of the new pipe line to transport water, the line had to cross several sections of the factory. The client initially had thought to cross the factory from the inside, but this was complex due to the large amount of machinery already installed. It would also require a lot of labor for the assembly of the connections, due to the length of the line.

Pexgol Solution

CMT La Laguna decided to install Pexgol pipes. The pipes were offered in sections of 100, 150 and 200 meters, which greatly expedited the installation, since it required fewer connections. On the other hand, it allowed to save costs since the engineering team of Pexgol suggested the installation of the line on the roof, being able to save on supports and labor for the connections.

The client would not have been able to do this with other plastic pipes for example, since the metal sheets of the ceilings becomes very hot in summer (up to 60°C) and these would not resist.

At the factory, it was important that the pipeline look as neat as possible, and having many accessories exposed Pexgol made sure to provide a complete and visually adequate solution. Electrofusion fittings, “t” fittings and elbows were provided.

Thanks to Pexgol, the following savings were made:

  • The Pexgol installation team went to the field and trained the maintenance team of the factory, so that they can do the installation themselves without hiring a third party to do so.
  • Pexgol lent the welding tools so that the client did not have to invest in equipment.
  • Pexgol lent an uncoiling equipment to speed up the installation.

Related Case Studies

Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019