Skip to content

Open Cast Mine Dewatering

Water Transportation through Shafts

Estudo de Caso Nº

39

Cliente

Agnico Eagle Pinos Altos Mine
Mexico

|

2017

Condições de Trabalho

300 psi, altitude dierence= 174 m, mine water with 15-20% solids.

Solução Pexgol

Pexgol SDR 7.4 225×30.8.

Aplicação

Dewatering.

Comprimento

225 meters.

Categorias

Water Transportation through Shafts

The Challenge

The ground water control system used at Pinos Altos Mine is trough dewatering, which is the method that better adjust to the characteristics of the mine work, furthermore it’s the more efficient and cost-effective if it’s handled the right way.

The fluid transportation associated costs in the mining industry represents an important percentage of the total cost of the operation, consequently the development of work schemes and a hydraulic system optimization, generates important savings on operational costs.

For the pumping system optimization the client designed a pool on level 28, that will gather the runoff water from the superior levels after pumping up to level 22.

Pexgol Solution

For this conduction line a Pexgol pipe was chosen, since it fulfilled the technical features that the job required. Due its ability to be supplied in long length coils, and its capacity to hold 175 meters of water column (249 psi), plus its easy-to-maneuver and installation capabilities (since the pipe was installed through the shafts) and its supplied long sections (which prevents head losses through the joints), the Pexgol pipe was the perfect solution. In addition, the Pexgol pipe roughness coefficient is lower than other pipes, therefore less friction losses and energy savings were encountered.

Estudos de Caso Relacionados

Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Process Plant: Transport of Leached Slurry

Barrick Gold – Pueblo Viejo
Dominican Republic

 | 

2018
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022