Open Cast Mine Dewatering

Water Transportation through Shafts

Estudo de Caso Nº

39

Cliente

Agnico Eagle Pinos Altos Mine
Mexico

|

2017

Condições de Trabalho

300 psi, altitude dierence= 174 m, mine water with 15-20% solids.

Solução Pexgol

Pexgol SDR 7.4 225×30.8.

Aplicação

Dewatering.

Comprimento

225 meters.

Categorias

Water Transportation through Shafts

The Challenge

The ground water control system used at Pinos Altos Mine is trough dewatering, which is the method that better adjust to the characteristics of the mine work, furthermore it’s the more efficient and cost-effective if it’s handled the right way.

The fluid transportation associated costs in the mining industry represents an important percentage of the total cost of the operation, consequently the development of work schemes and a hydraulic system optimization, generates important savings on operational costs.

For the pumping system optimization the client designed a pool on level 28, that will gather the runoff water from the superior levels after pumping up to level 22.

Pexgol Solution

For this conduction line a Pexgol pipe was chosen, since it fulfilled the technical features that the job required. Due its ability to be supplied in long length coils, and its capacity to hold 175 meters of water column (249 psi), plus its easy-to-maneuver and installation capabilities (since the pipe was installed through the shafts) and its supplied long sections (which prevents head losses through the joints), the Pexgol pipe was the perfect solution. In addition, the Pexgol pipe roughness coefficient is lower than other pipes, therefore less friction losses and energy savings were encountered.

Estudos de Caso Relacionados

Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022