Skip to content

Newmont’s Water Transportation Revolution with Pexgol Pipes

Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Estudo de Caso Nº

132

Cliente

Newmont Corporation
Argentina

|

2018

Condições de Trabalho

Soothills soil

Solução Pexgol

Pexgol 65, 75, 90, 110, 160, 200, 250 mm; classes 10, 12 & 15

Aplicação

Water transportation

Comprimento

5500 m / 18045 ft

Categorias

Newmont’s Water Transportation Revolution with Pexgol Pipes

The Challenge

Newmont Corporation, the world’s largest gold mining company, faced a significant challenge at its Cerro Negro unit in Santa Cruz, Argentina. The task at hand involved the transportation of water across challenging foothills terrain, a critical aspect of its mining operations. Given the demanding conditions, the ideal solution required pipes with superior durability, quality assurance for water installations, and agility for deployment and assembly. The initial plan involved over 300 joints, each representing a potential point of failure, and thus, a high risk to operational efficiency and reliability.

Pexgol Solution

Pexgol emerged as the most suitable solution for this task. Its range of pipes – Pexgol 63, 75, 90, 110, 160, 200, and 250 in classes 10, 12, and 15 – was chosen for their unmatched resilience, quality, and ease of installation. By supplying the pipes in rolls, several joints were eliminated from the pipeline, significantly reducing the risk of failure and decreasing installation time by 80% compared to other plastic pipes.

Pexgol’s permanent consultancy and training for the installers, coupled with its quick product availability, made it the perfect choice for Newmont Corporation. Additionally, Pexgol’s unique ability to avoid joints contributed to the ease, agility, and security of the pipeline, making cross-linked polyethylene (PEX) the most versatile and cost-effective solution for this project.

The installation process unfolded seamlessly. Newmont Corporation facilitated the uncolling of the Pexgol pipe coils, initially estimated to use 250 joints. The timeline for the installation was duly adhered to, with the entire pipeline spanning 5500 meters (approximately 18045 feet).

The utilization of Pexgol pipes effectively addressed Newmont Corporation’s water transportation needs, optimizing their gold mining operations’ efficiency, and contributing to its sustainable mining practices.

Estudos de Caso Relacionados

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Carriage of Chemicals at Sea Port

Ashdod Sea Port
Israel

 | 

2016
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Record-time intervention that avoided operational losses in a dehydration plant.

Critical Pipeline Replacement in Dehydration Plant with Operational Continuity

Petróleos Sudamericanos
Argentina

 | 

2025
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016
Pexgol enabled a safe and efficient installation across a highly constrained refinery layout.

Nitrogen Transport in a Complex Industrial Environment

YPF
Argentina

 | 

2025
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019