Fast and Reliable Solution for Winemaking Processes

How Pexgol streamlined water transportation at Zuccardi Winery

Case Study Nº

172

Customer

Zuccardi Winery
Argentina

|

2024

Working Conditions

Temperature: Ambient | Flow rate: 150 L/min | Pressure: 2 bar | Fluid: Potable water

Pexgol Pipes

Pexgol 90 mm, class 15

Application

Potable water transport

Lenght

120 m / 393 ft

Categories

Fast and Reliable Solution for Winemaking Processes

The Challenge

Zuccardi Winery, internationally acclaimed for its innovation and quality in wine production, needed to implement a potable water transport line to supply both consumption and vinification processes. The challenge was to connect the storage tanks—located in a separate building—to the main plant through a system that ensured a fast, safe, and efficient installation. Additionally, the solution had to minimize leakage risks while optimizing installation time and costs.

The terrain conditions called for a reliable piping system that did not require a sand bed for burial and could be handled easily, considering operational and space constraints around the winery.

The Solution

Zuccardi selected 90 mm Pexgol class 15 pipes for the project. This decision was based on Pexgol’s key advantages, including:

  • Rapid Installation: The 120 meters of pipe were uncoiled and laid out in just 20 minutes.
  • Fewer Joints: Thanks to the long-length coil format, no joints were needed along the run, significantly reducing leakage risks and associated costs.
  • Easy Handling: The lightweight material enabled efficient transport and installation, even under limited operational conditions.
  • Strength and Adaptability: The pipe required no sand bed for burial, simplifying the installation process.

The final installation was carried out two days after trench preparation and took only 2 hours, including burial and backfilling. Both ends of the pipeline were connected using flanged couplings to ensure system integrity.

Related Case Studies

Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Монтаж труб Pexgol для дренажа в подземном руднике.

Высоконапорный дренаж в подземном руднике

Рудник Охос-дель-Саладо — Lundin Mining
Чили

 | 

2018
Trial Demonstrates Superior Wear Resistance in Sea Water + Ash Slurry Conditions.

Unmatched Durability in Harsh Slurry: Pexgol Outperforms Steel

Tata Power
India

 | 

2023
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018
A Challenging Project That Eliminated Booster Stations Thanks to Pexgol’s Flexibility.

Vertical Solution for Mine Dewatering in Fresnillo

Fresnillo
Mexico

 | 

2025