Optimization of Lithium Brine Transportation

Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Case Study Nº

143

Customer

Puna Mining
Argentina

|

2022

Working Conditions

Flow: 77m³/h | Pressure: 60 psi

Pexgol Pipes

Pexgol 2”, 5” & 6”, class 15

Application

Transport of raw brine

Lenght

2 km

Categories

Optimization of Lithium Brine Transportation

The Challenge

Puna Mining S.A., a pioneer in high-quality battery-grade lithium carbonate production (99.5% purity) in Argentina, faced operational challenges with its brine transportation system. Founded in 2017 by Pablo Alurralde and later forming a joint venture with Argosy Minerals Ltd., the company was committed to utilizing cutting-edge technology in its production processes. However, their existing PVC piping presented significant limitations, requiring constant maintenance, frequent pipe replacements, and struggling with ongoing crystallization issues, which directly affected efficiency and increased operational costs.

Pexgol Solution

Pexgol stepped in with a tailored solution to address Puna Mining’s challenges.
The introduction of Pexgol pipes of 6, 2, and 5 inches over a 2-kilometer stretch was designed to meet the specific demands of raw brine transportation.
The complete installation was accomplished in just three days, highlighting the ease and efficiency of Pexgol pipes.
ArgPex provided on-site training to ensure a smooth and optimized installation process.

Benefits of Switching to Pexgol
By adopting Pexgol pipes, the following advantages were realized:

  • Rapid installation
  • High chemical and corrosion resistance
  • Material flexibility
  • Long lifespan
  • Reduced thermal conductivity
  • Lightweight pipes
  • Availability in long rolls for easier handling and installation

Related Case Studies

A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
В аэропорту Гайаны был установлен наружный гидрант и спринклеры внутри помещений

Линия водоснабжения и пожарной воды

Международный аэропорт Cheddi Jagan
Гайана

 | 

2018
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Транспортировка пластовой воды с углеводородами.

Транспортировка пластовой воды

ROCH
Аргентина

 | 

2015