Optimization of Lithium Brine Transportation

Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Estudo de Caso Nº

143

Cliente

Puna Mining
Argentina

|

2022

Condições de Trabalho

Flow: 77m³/h | Pressure: 60 psi

Solução Pexgol

Pexgol 2”, 5” & 6”, class 15

Aplicação

Transport of raw brine

Comprimento

2 km

Categorias

Optimization of Lithium Brine Transportation

The Challenge

Puna Mining S.A., a pioneer in high-quality battery-grade lithium carbonate production (99.5% purity) in Argentina, faced operational challenges with its brine transportation system. Founded in 2017 by Pablo Alurralde and later forming a joint venture with Argosy Minerals Ltd., the company was committed to utilizing cutting-edge technology in its production processes. However, their existing PVC piping presented significant limitations, requiring constant maintenance, frequent pipe replacements, and struggling with ongoing crystallization issues, which directly affected efficiency and increased operational costs.

Pexgol Solution

Pexgol stepped in with a tailored solution to address Puna Mining’s challenges.
The introduction of Pexgol pipes of 6, 2, and 5 inches over a 2-kilometer stretch was designed to meet the specific demands of raw brine transportation.
The complete installation was accomplished in just three days, highlighting the ease and efficiency of Pexgol pipes.
ArgPex provided on-site training to ensure a smooth and optimized installation process.

Benefits of Switching to Pexgol
By adopting Pexgol pipes, the following advantages were realized:

  • Rapid installation
  • High chemical and corrosion resistance
  • Material flexibility
  • Long lifespan
  • Reduced thermal conductivity
  • Lightweight pipes
  • Availability in long rolls for easier handling and installation

Estudos de Caso Relacionados

Improving the efficiency of salmon farming with the superior solution of Pexgol pipes.

Pexgol’s Pipe Solution Enhances Salmon Farming

Mowi
Chile

 | 

2021
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013