Vertical Drain in Underground Mine

Installation of Pexgol Pipes for Drainage of an Underground Mine

Case Study Nº

67

Customer

Meridian Mine — Faena El Peñón
Chile

|

2018

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), Class 15 | Pexgol 160 mm (6”), Class 19 | Pexgol 200 mm (8”), Class 26.7

Application

Mine Dewatering

Lenght

800 m

Categories

The Challenge

The Meridian mine (Faena El Peñón) required the installation of a line for the drainage of high-pressure water from the lower level of the mine, passing through the vertical ventilation chimney with a height of 150 meters, continuing through the interior of the mine until an outdoor pool.

Pexgol Solution

The client decided to install 800 m of Pexgol pipes in three di erent sizes:
Pexgol 160 mm (6”) Class 15, 160 mm (6”) Class 19 and 200 mm (8”) Class 26.7.
The installation was very simple:

  • Lifting was carried out in the ventilation chimney.
  • Mechanical connections were used that did not require special tools for installation.
  • In the upper area the pipes were placed on supports provided by the mining company.

Pexgol was selected due to its capabilities:

  • Possibility of supply in long lengths minimizing the connections to only 4.
  • Ability to withstand the drag of more than 5 km from outside to the final assembly point inside the underground mine.
  • Ability to withstand creep involved in vertical mounting of 150 meters.

Related Case Studies

Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025
Прокладка подземных труб для транспортировки воды по дороге рудника.

Транспортировка воды по дороге рудника

CODELCO — Рудник Андина
Чили

 | 

2019
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
Уменьшение нарастания материала в линиях рассола и раствора кислоты

Переработка полезных ископаемых. Транспортировка рассола

Компания SQM, шахта Pedro Valvidia
Чили

 | 

2010
Química del Rey replaced a corroded steel column with a Pexgol line, achieving a faster, safer, and more durable installation.

Reliable Solution for Deep Wells in Corrosive Environments

Química del Rey
Mexico

 | 

2022
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024