Vertical Drain in Underground Mine

Installation of Pexgol Pipes for Drainage of an Underground Mine

Case Study Nº

67

Customer

Meridian Mine — Faena El Peñón
Chile

|

2018

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), Class 15 | Pexgol 160 mm (6”), Class 19 | Pexgol 200 mm (8”), Class 26.7

Application

Mine Dewatering

Lenght

800 m

Categories

The Challenge

The Meridian mine (Faena El Peñón) required the installation of a line for the drainage of high-pressure water from the lower level of the mine, passing through the vertical ventilation chimney with a height of 150 meters, continuing through the interior of the mine until an outdoor pool.

Pexgol Solution

The client decided to install 800 m of Pexgol pipes in three di erent sizes:
Pexgol 160 mm (6”) Class 15, 160 mm (6”) Class 19 and 200 mm (8”) Class 26.7.
The installation was very simple:

  • Lifting was carried out in the ventilation chimney.
  • Mechanical connections were used that did not require special tools for installation.
  • In the upper area the pipes were placed on supports provided by the mining company.

Pexgol was selected due to its capabilities:

  • Possibility of supply in long lengths minimizing the connections to only 4.
  • Ability to withstand the drag of more than 5 km from outside to the final assembly point inside the underground mine.
  • Ability to withstand creep involved in vertical mounting of 150 meters.

Related Case Studies

Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Замена трубы ПЭНД на трубу компании Pexgol

Транспортировка сжатого воздуха

Шахта компании Saucito S.A. de C.V.
Мексика

 | 

2017
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Уменьшение нарастания материала в линиях рассола и раствора кислоты

Переработка полезных ископаемых. Транспортировка рассола

Компания SQM, шахта Pedro Valvidia
Чили

 | 

2010