Advanced piping solutions for handlingscaling fluids

Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Case Study Nº

157

Customer

Barrick Gold
Dominican Republic

|

2023

Working Conditions

Temperature: 65°C / 149°F | Flow: 250 m³/h | Pressure: 7 bar

Pexgol Pipes

Pexgol 315 mm, Class 12

Application

SCT discharge line in cooling towers

Lenght

35 m / 114 ft

Categories

Advanced piping solutions for handlingscaling fluids

The Challenge

Barrick Gold Corporation, at its Pueblo Viejo mining unit, faced a significant challenge in its operation. The company was using 12” SCH 40 carbon steel pipes for the transportation of slurry with lime sludge in its SCT discharge line at the cooling towers. This method presented several problems, primarily due to its chemical composition, the fluid was highly scaling. The scale reduced the inner diameter of the pipes by 30% to 40% over an approximate three-month period, severely affecting performance and increasing the energy consumption of the pumping system. Additionally, maintenance required dismantling the lines, cleaning them with high-pressure equipment, and a team of 10 operators for about two weeks, resulting in high operational and maintenance costs.

The Solution

In search of an innovative solution, Barrick Pueblo Viejo opted to implement 315 mm Class 12 Pexgol pipes, with a length of 35 meters for a pilot test. Pexgol piping, known for its high resistance to abrasion, corrosion, and scaling, was presented as the alternative for this challenging environment. Three-meter sections of the pipe were flown in, and connections were made using electrofusion couplings and flanged couplings for integration into the existing system through flanged joints.

The installation was completed in approximately one day, including the training of staff for field welding. This rapid installation minimized interruptions in the operations of Barrick Pueblo Viejo, allowing for a smooth transition to the new piping system.

Since the implementation of Pexgol, scaling has significantly decreased. The pipes have been operating for 9 months without signs of scaling, resulting in a significant reduction in operational and maintenance costs. The total changeover of the existing line can generate savings of 200,000 USD per year in maintenance.

Related Case Studies

Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Отвод воды из шахты

Отвод воды из шахты

Компания El Peñón Yamana Gold, шахта Meridian
Чили

 | 

2016
Монтаж сети пожаротушения на нефтеперерабатывающем заводе.

Водоснабжение для пожарных сетей

КНМ
Аргентина

 | 

2021
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Фитинги Pexgol для транспортировки рассола в бразильской химической компании.

Высокая коррозионная стойкость к рассолу

Unipar Carbocloro
Бразилия

 | 

2019