Drinking Water on Sloping Terrain

Installation of a drainage system between a well and a mining dam.

Case Study Nº

84

Customer

AquaMag
Colombia

|

2019

Working Conditions

Temperature: ambient | Pressure: 3 bar | Sloping terrain

Pexgol Pipes

Pexgol 160 mm (6″), class 10

Application

Potable water transport

Lenght

188 m

Categories

Installation of a drainage system between a well and a mining dam.

The Challenge

AquaMag, the aqueduct and sewerage company of Santa Rosa de Lima (Colombia), uses pipes that are exposed on the lands or farms of the inhabitants of this population to transport raw water for treatment. Due to uncontrolled agricultural burning on the farms, a section of the existing HDPE pipe was burned.

AquaMag needed to continue supplying drinking water to 1,600 people, transporting 10 liters per second, from the San Sebastián river to Santa Rosa de Lima.

The Solution

The client ultimately decided to install a Pexgol pipe due to its ease of handling on complex terrain, resistance to wear, UV rays (since the pipe was exposed), longer life compared to other materials, and the ability to supply it in rolls, which allowed for fewer joints.

Due to the terrain conditions, the installation took 10 days, which would have taken 25 days if another type of pipe had been used.

43 electrofusion joints were made, as sections of HDPE pipe were replaced by Pexgol in different areas. In critical points, a complete section of Pexgol pipe was used.

Related Case Studies

Improving drainage in the Media Luna mine with Pexgol.

Overcoming Geotechnical Challenges with Pexgol at Media Luna

Minera Media Luna
Mexico

 | 

2023
Осушение сквозных шахтных стволов на подземном свинцово-цинковом руднике.

Осушение сквозных шахтных стволов

Esan Eczacibasi Endustriyel Hammaddeler
Турция

 | 

2019
Potable Water Supply on Harsh Terrain

Снабжение питьевой водой в труднопроходимой местности

Компания водоснабжения Mekorot / Beit Shemesh Water Company
Израиль

 | 

2017
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Трубы Pexgol для транспортировки фторкремниевой кислоты.

Транспортировка фторкремниевой кислоты

Фосфатный рудник — ICL Rotem
Израиль

 | 

1995
Транспортировка пластовой воды с углеводородами.

Транспортировка пластовой воды

ROCH
Аргентина

 | 

2015