Elevating Efficiency in Hydrocarbon Exploitation

Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Case Study Nº

131

Customer

Aconcagua Energía
Argentina

|

2023

Working Conditions

Temperature: 35°C / 95°F | Flow: 80 m³/hour | Pressure: 10 Kg/cm²

Pexgol Pipes

Pexgol 110 mm (4″), class 24

Application

Formation water

Lenght

1280 m / 4199 ft

Categories

Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

The Challenge

As an independent energy company that vertically integrates all operations, Aconcagua Energía S.A. was seeking ways to enhance efficiency in its exploration and exploitation of conventional hydrocarbons. The primary challenge lay in the management of their formation water transportation line. An existing carbon steel pipe, used for this project, faced significant corrosion due to the transport of formation water, necessitating its removal from service. The project required a piping system that could withstand the corrosive environment, perform under operational conditions, and could be installed quickly and efficiently over a distance of approximately 1280 meters (or around 4199 feet).

Pexgol Solution

Pexgol was chosen as the ideal piping solution for Aconcagua Energía S.A. A Pexgol pipe of 110 mm diameter, class 24, renowned for its high resistance to chemicals and corrosion, was provided. Despite the project’s length and the piping system’s operational conditions—35°C (95°F) temperature, 80 m³/h flow rate, and 10 Kg/cm² pressure—Pexgol pipe’s durability and performance were unflinching.

One of the main benefits of Pexgol is its ease and speed of installation. The installation was completed in two days. Each morning, with the assistance of a backhoe, each roll was extended in less than an hour. The afternoons were spent burying the pipes at road crossings.
Another advantage of Pexgol pipes is the provision of long lengths that could be transported in rolls, minimizing the need for joints and reducing installation time.

Mechanical double connectors and GP flanged couplers were used in the installation, further ensuring a secure and leak-free system.
With Pexgol pipes, Aconcagua Energía S.A. successfully upgraded its formation water transportation system, reinforcing its commitment to efficiency and productivity. The client has also expressed a desire to replace their PRFV (Fiberglass Reinforced Plastic) pipe aqueducts with PEX, given the challenges they faced during the transportation and installation of PRFV. This successful transition attests to
Pexgol’s superiority and reliability as a piping solution in the energy sector.

Related Case Studies

Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
Монтаж труб Pexgol для транспортировки горячей воды

Горячее водоснабжение

Hilton
Израиль

 | 

2020
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Работа с высоким давлением и предельными температурами окружающей среды

Транспортировка воды на медном руднике

Рудник Zaldivar SPA
Чили

 | 

2018