Evolving Mine Operations with Pexgol Piping

The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Case Study Nº

150

Customer

Peña Colorada
Mexico

|

2023

Working Conditions

Temperature: Ambient Flow: 410 m^3/h | Pressure: 7 bar | Fluid components: Rainwater Pipe exposed to the sun

Pexgol Pipes

Pexgol 10″, SDR 11

Application

Mine Dewatering

Lenght

500 m / 1640 ft

Categories

Evolving Mine Operations with Pexgol Piping

The Challenge

Peña Colorada, a leading company dedicated to the exploration, exploitation, and beneficiation of iron ore, met with a unique operational hurdle at their open-pit mine in Mexico. Historically, they employed HDPE piping systems for mine drainage.

However, as the mine’s surface continuously evolved, they faced the challenge of constantly relocating their pumps and piping. Each relocation with their steel pipes required a significant workforce, two cranes, and a special transportation mechanism for the pipe. Furthermore, they had to ensure very broad curves to prevent leakage at the joints.

Pexgol Solution

Pexgol, recognizing the inherent challenges with the existing piping system, introduced their 10” SDR 11 pipes. These were designed not only to address the drainage needs but to offer unmatched flexibility in a mining environment where surfaces change frequently. The Pexgol pipes could be easily dragged for relocation across the mine’s floor without compromising operational pressures. Moreover, these pipes could effortlessly follow any path necessary for optimal drainage.

During installation, as the pipe was being unrolled, it was simultaneously positioned where it was to be installed, connecting the pump to the discharge pipe. The entire process was completed in a single shift without any special surface preparation. The mine, which notably produces steel and even manufactures steel pipes, chose Pexgol due to its superior corrosion resistance and installation flexibility.

Related Case Studies

 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Транспортировка речной воды по пересеченной местности.

Транспортировка воды по пересеченной местности

Southern Copper Corporation
Перу

 | 

2019
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

Fresnillo Plc.
Mexico

 | 

2025
Монтаж сети пожаротушения на нефтеперерабатывающем заводе.

Водоснабжение для пожарных сетей

КНМ
Аргентина

 | 

2021
850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

Raquet Club Lake Chapala
Mexico

 | 

2024