Skip to content

High-pressure fluid transport

High-pressure water transport for the Southern Pit in a copper and zinc mine.

Case Study Nº

156

Customer

Minera Antapaccay
Peru

|

2023

Working Conditions

Exposed pipe with 30 bar (435 PSI) repump system

Pexgol Pipes

Pexgol 355 mm (14”), class 30

Application

Drain water transport

Lenght

270 m / 885 ft

Categories

High-pressure fluid transport

The Challenge

Minera Antapaccay faced the challenge of laying a pipeline over the slope of the Southern Pit from level 3870 to level 3632; for its project to drain groundwater from the bottom of the pit to connect to the water network for the plant, located in the mine area. Given the morphology of the slope in the terrain and the difference in heights (238 meters), a pipeline was required that would provide safety for working with high pressures and that could be exposed to the sun and low temperatures without the need to bury it.

The Solution

It was decided to install Pexgol since it is supplied in roll format, in this case up to 90 m in length. Compared to steel and HDPE, which are supplied in 12 or 14-meter sections, this supply format minimized labor and the likelihood of failure. Likewise, the potential for making joints on the slope’s body was reduced, decreasing the exposure of personnel to high-risk work. The laying was carried out using the brand’s equipment, making use of a pipe uncoiler, yellow line equipment, and manual pulling equipment (tirfor), due to the limited space for unrolling. Connections were made using electrofusion couplings and stub-ends.

Related Case Studies

How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022
Optimization of Water Systems in the Energy Industry.

“Threading” Pexgol Pipes

Pluspetrol
Argentina

 | 

2023
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Монтаж дренажной системы между дамбами на медном руднике.

Транспортировка воды между дамбами

CODELCO — Рудник Эль-Тениенте
Чили

 | 

2019
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025