Skip to content

Natural Gas Transportation with Pexgol

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Case Study Nº

110

Customer

YPF
Argentina

|

2022

Working Conditions

Fluid: Condensate natural gas | Temperature: 35°C / 95°F | Minimum Pressure: negative (vacuum) | Maximum Pressure: 2 kg/cm2 | Flow: 40.000 standard m3/d

Pexgol Pipes

Pexgol 160 mm (6”) , class 10

Application

Natural gas transportation

Lenght

600 m / 1968 ft

Categories

The Challenge

YPF is an Argentine energy company dedicated to the exploration, exploitation, distillation, distribution and production of electricity, gas, oil and other products related to the industry.

In its Vacas Muertas oil field, province of Mendoza (Argentina), the company had to replace 600 meters of carbon steel pipe, located between the crude oil treatment plant (PTC) and the gas compression plant. Over time, the section had reduced its internal diameter at different points of the trace, due to encrustations caused by corrosion and deposits resulting from humid gas condensation. This reduced the gas flow, and there was a risk of reaching a total obstruction of the flow.

As it is a continuous process, which does not allow accumulation of gas, it was necessary to carry out the work as quickly as possible with the shortest time of interruption of the flow to the gas plant.

Pexgol Solution

It was decided to install Pexgol pipes, which allow a quick installation and with the minimum amount of resources. This way, the corrosion process will be avoided, as well as the accumulation of scale due to the low absolute roughness of the internal walls of Pexgol pipes, allowing a continuous flow without obstructions over time.

The installation was completed with 3 coil of Pexgol 160 mm Class 10 pipe, the joints were made with electrofusion couplings, and the steel transitions with Pexgol flaring (stub-ends).

The installation was carried out in two working days, aerially on existing trestles, and with a minimum interruption of the process. The resources used were minimal: 3 operators with an uncoiler, a hydrocrane and a backhoe. The replacement with carbon steel would have taken a month with the company’s operational resources, and with a total cost 6 times higher than that required for the materials and installation with Pexgol pipes.

Related Case Studies

Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023
Линия питьевой воды высокого давления

Линия питьевой воды высокого давления

Компания Antofagasta Minerals, шахта Pelambres
Чили

 | 

2014
Транспортировка воды c сульфидными и кобальтовыми частицами

Транспортировка воды и сульфидов

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2015
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Транспортировка пульпы пальмового масла при 95 °C.

Транспортировка пульпы пальмового масла

Компания Loma Fresca
Колумбия

 | 

2017
Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023