Skip to content

Natural Gas Transportation with Pexgol

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Case Study Nº

110

Customer

YPF
Argentina

|

2022

Working Conditions

Fluid: Condensate natural gas | Temperature: 35°C / 95°F | Minimum Pressure: negative (vacuum) | Maximum Pressure: 2 kg/cm2 | Flow: 40.000 standard m3/d

Pexgol Pipes

Pexgol 160 mm (6”) , class 10

Application

Natural gas transportation

Lenght

600 m / 1968 ft

Categories

The Challenge

YPF is an Argentine energy company dedicated to the exploration, exploitation, distillation, distribution and production of electricity, gas, oil and other products related to the industry.

In its Vacas Muertas oil field, province of Mendoza (Argentina), the company had to replace 600 meters of carbon steel pipe, located between the crude oil treatment plant (PTC) and the gas compression plant. Over time, the section had reduced its internal diameter at different points of the trace, due to encrustations caused by corrosion and deposits resulting from humid gas condensation. This reduced the gas flow, and there was a risk of reaching a total obstruction of the flow.

As it is a continuous process, which does not allow accumulation of gas, it was necessary to carry out the work as quickly as possible with the shortest time of interruption of the flow to the gas plant.

Pexgol Solution

It was decided to install Pexgol pipes, which allow a quick installation and with the minimum amount of resources. This way, the corrosion process will be avoided, as well as the accumulation of scale due to the low absolute roughness of the internal walls of Pexgol pipes, allowing a continuous flow without obstructions over time.

The installation was completed with 3 coil of Pexgol 160 mm Class 10 pipe, the joints were made with electrofusion couplings, and the steel transitions with Pexgol flaring (stub-ends).

The installation was carried out in two working days, aerially on existing trestles, and with a minimum interruption of the process. The resources used were minimal: 3 operators with an uncoiler, a hydrocrane and a backhoe. The replacement with carbon steel would have taken a month with the company’s operational resources, and with a total cost 6 times higher than that required for the materials and installation with Pexgol pipes.

Related Case Studies

Транспортировка высококоррозийных материалов от сгустителей на установку нейтрализации

Транспортировка коррозионных материалов

Компания Moa Nickel S.A, Sherritt
Куба

 | 

2015
Replacement of a Drainage Line in an Underground Mine.

Дренаж в подземном руднике

Atacama Kozan
Чили

 | 

2019
Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
Transport of acid slurry at high temperatures

Транспортировка суспензии

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2012
Работа с высоким давлением и предельными температурами окружающей среды

Транспортировка воды на медном руднике

Рудник Zaldivar SPA
Чили

 | 

2018
Использование системы труб Pexgol для кормления лосося в сравнении с трубами ПЭНД

Транспортировка пищевых продуктов трубами Pexgol в сравнении с трубами ПЭНД

Компания Marine Farms
Чили

 | 

2017