Skip to content

Natural Gas Transportation with Pexgol

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Estudo de Caso Nº

110

Cliente

YPF
Argentina

|

2022

Condições de Trabalho

Fluid: Condensate natural gas | Temperature: 35°C / 95°F | Minimum Pressure: negative (vacuum) | Maximum Pressure: 2 kg/cm2 | Flow: 40.000 standard m3/d

Solução Pexgol

Pexgol 160 mm (6”) , class 10

Aplicação

Natural gas transportation

Comprimento

600 m / 1968 ft

Categorias

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

The Challenge

YPF is an Argentine energy company dedicated to the exploration, exploitation, distillation, distribution and production of electricity, gas, oil and other products related to the industry.

In its Vacas Muertas oil field, province of Mendoza (Argentina), the company had to replace 600 meters of carbon steel pipe, located between the crude oil treatment plant (PTC) and the gas compression plant. Over time, the section had reduced its internal diameter at different points of the trace, due to encrustations caused by corrosion and deposits resulting from humid gas condensation. This reduced the gas flow, and there was a risk of reaching a total obstruction of the flow.

As it is a continuous process, which does not allow accumulation of gas, it was necessary to carry out the work as quickly as possible with the shortest time of interruption of the flow to the gas plant.

Pexgol Solution

It was decided to install Pexgol pipes, which allow a quick installation and with the minimum amount of resources. This way, the corrosion process will be avoided, as well as the accumulation of scale due to the low absolute roughness of the internal walls of Pexgol pipes, allowing a continuous flow without obstructions over time.

The installation was completed with 3 coil of Pexgol 160 mm Class 10 pipe, the joints were made with electrofusion couplings, and the steel transitions with Pexgol flaring (stub-ends).

The installation was carried out in two working days, aerially on existing trestles, and with a minimum interruption of the process. The resources used were minimal: 3 operators with an uncoiler, a hydrocrane and a backhoe. The replacement with carbon steel would have taken a month with the company’s operational resources, and with a total cost 6 times higher than that required for the materials and installation with Pexgol pipes.

Estudos de Caso Relacionados

Replacement of Carbon Steel Pipe for a Pexgol Pipe

Water Transportation

Cargill
Mexico

 | 

2017
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Pexgol pipe was selected for the assembly of a muddy water transport line for a palm oil processing company.

Transport of Muddy Water for Palm Oil Extractor

Extractora Poligrow
Colombia

 | 

2022
Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013