Skip to content

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Case Study Nº

177

Customer

Kimex
Mexico

|

2025

Working Conditions

Temperature: 16°C – 31°C (Ambient) | Pressure: 3 bar | Flow Rate: 115 m³/hr | Fluid: Boiler feedwater

Pexgol Pipes

Pexgol 4″ SDR 11

Application

Water conveyance for power plant commissioning

Lenght

600 m / 1968 ft

Categories

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

The Challenge

Kiewit Corp., through its subsidiary Kimex SA de CV, faced a critical requirement during the construction of the CCC Tuxpan Phase 1 combined-cycle power plant in Mexico. To initiate testing and commissioning, the new facility needed to be supplied with boiler feedwater—a fluid requiring high purity and specific properties.

The challenge: the site under construction lacked an operational water treatment system, and any solution had to be immediate, highly reliable, and compatible with Kiewit’s rigorous safety protocols. Additionally, the piping had to withstand conditions typical of an active construction environment.

The Solution

Pexgol proved to be the ideal choice. In just one day, 600 meters of 4” SDR 11 Pexgol pipe were installed using only standard on-site machinery and tools, with no need for specialized equipment. The very next day, the system was operational, enabling the project team to start equipment testing without delay.

The line transported boiler feedwater at 3 bar of pressure and a flow rate of 115 m³/h, operating smoothly within the site’s ambient temperature range of 16°C to 31°C.

A key success factor was Kiewit’s validation of internal safety protocols. Although using coiled piping was new to their team, the installation was incident-free, demonstrating Pexgol’s safety and reliability even in demanding construction environments.

Key Benefits:

  • Rapid installation without specialized equipment
  • Flexible and impact-resistant material, ideal for active worksites
  • Excellent chemical and corrosion resistance
  • Lightweight and easy to handle
  • Full compliance with international safety protocols

Fittings Used:

  • Flared End / Stub End
  • Loose Flange
  • Fixpoint Bridge

Related Case Studies

Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Установка труб на горе

Транспортировка талых стоков

Компания Codelco Andina, проект TADA 1-2
Чили

 | 

2013
Дренаж воды из жесткой почвы

Отвод воды в карьере

Timmins Gold Corp Group, шахта Molimentales
Мексика

 | 

2016
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
Монтаж труб Pexgol для транспортировки пластовой воды (с газом и минералами)

Газовые скважины: обработка пластовой воды

Canacol
Колумбия

 | 

2018