Water Lines — High Pressure Water Feed Lines

Water line feed from wells to mine

Case Study Nº

5

Customer

Yamana Gold, Meridian Mine
Chile

|

2012

Working Conditions

High pressure (over 24 bar), corrosion and ambient temperature at 40°C/104°F. The first 2,750 meters of pipes were covered in sand, the last 2,750 meters were exposed to the sun.

Pexgol Pipes

Pexgol 225×30.8, Class 24.

Application

Dewatering.

Lenght

5,500 meters.

Categories

The Challenge

The high pressure and corrosion caused constant failure of the two initial parallel steel pipelines and serious threats to the production process.

One steel pipeline was out of service for at least two years and the other suffered from severe corrosion. Since this was the only main line transporting water to the production line, it was critical for the whole production process. The client required a highly durable and a quick install solution for non-stop performance

Pexgol Solution

The replacement of the steel pipeline with Pexgol’s flexible and high resistance to corrosion pipe solution eliminated previous failures. In addition, Pexgol supplied easy-to-install longer pipes.

The client is so pleased with the solution that he will be replacing the HDPE pipes that are part of this line as well.

Related Case Studies

Замена трубы ПВХ трубой Pexgol

Транспортировка сульфида натрия

Magnelec S.A. de C.V.
Мексика

 | 

2018
A Challenging Project That Eliminated Booster Stations Thanks to Pexgol’s Flexibility.

Vertical Solution for Mine Dewatering in Fresnillo

Fresnillo
Mexico

 | 

2025
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
Монтаж труб Pexgol для системы сжатого воздуха.

Система сжатого воздуха

Типография Rav-Gon
Израиль

 | 

2020
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022