Working Conditions

Pressure: 15 bars | Temperature: Ambient

Pexgol Pipes

Pexgol 180 (6″), 225 (8″) & 280 (12″) mm, Class 15

Application

Water transport for fire network

Lenght

1000 m / 3280 ft

Categories

The Challenge

Profertil, an Argentine company specializing in the manufacture of fertilizers, has a fire network that is more than 10 years old working with carbon steel pipes.

Given that the water they transport has a high chloride content, the lines were affected by corrosion and in many cases even with scale that obstructed the pipe by 50%.

Pexgol Solution

In order to have an efficient fire-fighting network, the Profertil project team opted for a plastic pipe that does not suffer from corrosion, with less possibility of incrustations and its installation does not require specialized machinery.

Likewise, given bad experiences with other types of pipes in relation to installation and operation, the maintenance team carried out pressure tests and resistance to external damage with a sample that was delivered to them.

Finally, 3 lines with Pexgol pipes were installed and it is scheduled in other stages to completely replace the fire network, a total estimate of 7 km.

Electrofusion joints and accessories were used to carry out the derivations and changes of direction.
In relation to other materials and considering that in several places where the pipe had to be buried, obstacles were found from cables and other pipes, the installation was successful.

Related Case Studies

Монтаж труб Pexgol для транспортировки пластовой воды (с газом и минералами)

Газовые скважины: обработка пластовой воды

Canacol
Колумбия

 | 

2018
Транспортировка пластовой воды с углеводородами.

Транспортировка пластовой воды

ROCH
Аргентина

 | 

2015
Transportation of brackish water to the main pumping station

Водопроводные линии — суровые природные условия

Работы на Мертвом море
Израиль

 | 

1993
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Горячий сильвинитовый насыщенный рассол с температурой 114 °C (237 °F)

Переработка минерального сырья — установка по переработке углекислого калия

ICL group, работы на Мертвом море
Израиль

 | 

1987
Монтаж труб Pexgol для вертикального дренажа

Вертикальный отвод вод

Полтавский ГОК, Ferrexpo
Украина

 | 

2019