Skip to content

Mining Drainage Lines

Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Case Study Nº

72

Customer

Lundin Mining – Alcaparosa Mine
Chile

|

2019

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), class 19

Application

Dewatering

Lenght

1000 m / 3280 ft

Categories

Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

The Challenge

Lundin Mining at Alcaparosa Mine had to install a drainage line for its underground mine, where the main problem they faced was lack of time. They needed a non-invasive installation of the pipeline in order to allow the continuity of the mining operation and get back to work in the shortest time possible.

Pexgol Solution

The client decided to install 1000 meters of Pexgol pipe that was supplied in two coils of 500 meters each.
Cross-linked polyethylene was chosen because of:

  • Its long-length supply format.
  • Ease of installation, thanks to the flexibility of the pipe that was easy to accommodate in the curves of the interior of the mine.
  • Short installation time to avoid stopping the mining operation.

Installation was quick and easy, uncoiling the full length of the pipeline and then dragging it into the mine.

Related Case Studies

Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013
Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
High Pressure potable water line

High Pressure Potable Water Line

Antofagasta Minerals, Pelambres Mine
Chile

 | 

2014
Installation of 3000 Meters Of PE-X Pipe for an Underground Mine.

Drainage Lines in Underground Mine

Lundin Mining – Candelaria Norte Mine
Chile

 | 

2020
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025