Skip to content

Water Drainage at an Open-Cast Mine

Water Drainage in Harsh Ground

Case Study Nº

32

Customer

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

|

2016

Working Conditions

Solar exposure, 14 bars.

Pexgol Pipes

Pexgol 225 mm, Class 15 (SDR 11).

Application

Water drainage.

Lenght

200 m.

Categories

Water Drainage In Harsh Ground

The Challenge

At “Molimentales” Mine in order to continue with their open-cast mining operations, it was necessary to drainage water from some sections in the ground. Formerly, the mine used an HDPE pipe of 12 meter sections, but they had constant issues due to leaks in the joints.

Pexgol Solution

A Pexgol pipe was provided, in 100 meters sections, in order to have less joints and thereby less leak risks.

Furthermore, the installation was fast and simple due to the lack of welds, and the pipes were dragged with the equipment that the mine already had available.

Related Case Studies

Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Pexgol enabled a safe and efficient installation across a highly constrained refinery layout.

Nitrogen Transport in a Complex Industrial Environment

YPF
Argentina

 | 

2025
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022