Nitrogen Transport in a Complex Industrial Environment

Pexgol enabled a safe and efficient installation across a highly constrained refinery layout.

Case Study Nº

190

Customer

YPF
Argentina

|

2025

Working Conditions

Temperature: 20°C | Pressure: 8 kg/cm² | Fluid: Gaseous nitrogen

Pexgol Pipes

Pexgol 110 mm (4”), Class 15

Application

Nitrogen

Lenght

2.2 km

Categories

Nitrogen Transport in a Complex Industrial Environment

The Challenge

YPF, Argentina’s leading energy company with integrated operations in exploration, production, refining, and commercialization of hydrocarbons, required the development of a new pipeline to transport nitrogen from Petroquímica Cuyo to its industrial operations at the Luján de Cuyo Refinery in Mendoza, Argentina.

The project demanded a reliable solution capable of operating with gaseous nitrogen at 20°C and 8 kg/cm² within a highly demanding industrial environment.

The main challenge was the pipeline routing. The line needed to cross the refinery from west to east, a complex task due to numerous existing interferences and strict safety protocols inherent to an active industrial facility.

Additionally, the total length of the project—2.2 km—required an efficient execution strategy to minimize intervention times and ensure a safe installation without disrupting ongoing refinery operations.

The Solution

For this project, Pexgol 110 mm Class 15 was selected as the optimal piping solution. Key advantages included fast installation, high chemical and corrosion resistance, long service life, and material flexibility.

The lightweight nature of the pipe, combined with the ability to supply it in long continuous coils, significantly reduced the number of joints required on site. This allowed the pipeline to be adapted efficiently to the refinery’s complex layout, optimizing maneuverability and minimizing interference during installation.

The system incorporated electrofusion couplers, loose flanges, and flared ends / stub ends, ensuring a reliable and secure connection throughout the pipeline.

Thanks to careful planning and the operational advantages of the Pexgol system, the full 2.2 km pipeline was installed in just 10 days.

As a final stage, a pneumatic integrity test at 3.5 kg/cm² was successfully performed, ensuring complete tightness of the system prior to commissioning.

The result was a safe, efficient, and reliable solution for nitrogen transport within one of Argentina’s main refineries, once again demonstrating Pexgol’s capability to perform in applications where installation speed, flexibility, and operational safety are critical.

Related Case Studies

High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017