Alumina Plant: Ore Slurry Transportation

Transportation of Bauxite Ore Slurry at 95°C / 203°F

Case Study Nº

52

Customer

Urals Alumina Plant – Rusal
Russia

|

2013

Working Conditions

High temperature

Pexgol Pipes

Pexgol 160 mm Class 15

Application

Slurry Transportation

Lenght

20 m

Categories

Transportation of Bauxite Ore Slurry at 95°C / 203°F

The Challenge

At Urals Alumina Plant, they required to renovate their carbon steel pipes where they transport bauxite ore slurry at 95°C / 203°F. Every year these lines were suffering from sedimentation problems and it was necessary to clean them every three months, involving man power and high costs.

Pexgol Solution

The client decided to replace the carbon steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance, lowering also costs.

The Pexgol pipes have been checked annually and even after 4,5 years of exploitation, the pipes have shown positive results. They don’t have to clean the pipes any more.

Related Case Studies

Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021