Skip to content

Alumina Plant: Ore Slurry Transportation

Transportation of Bauxite Ore Slurry at 95°C / 203°F

Case Study Nº

52

Customer

Urals Alumina Plant – Rusal
Russia

|

2013

Working Conditions

High temperature

Pexgol Pipes

Pexgol 160 mm Class 15

Application

Slurry Transportation

Lenght

20 m

Categories

Transportation of Bauxite Ore Slurry at 95°C / 203°F

The Challenge

At Urals Alumina Plant, they required to renovate their carbon steel pipes where they transport bauxite ore slurry at 95°C / 203°F. Every year these lines were suffering from sedimentation problems and it was necessary to clean them every three months, involving man power and high costs.

Pexgol Solution

The client decided to replace the carbon steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance, lowering also costs.

The Pexgol pipes have been checked annually and even after 4,5 years of exploitation, the pipes have shown positive results. They don’t have to clean the pipes any more.

Related Case Studies

Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Sewage Water Transportation with 300 PPM Hydrogen Peroxide

Sewage Water Transportation

BorsodChem
Hungary

 | 

2011
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010
Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017