Dewatering Through Shafts

Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Case Study Nº

81

Customer

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

|

2019

Working Conditions

Pressure: 20 bars | Ambient temperature

Pexgol Pipes

Pexgol 160 mm (6”), class 24

Application

Dewatering

Lenght

350 m / 1148.29 ft

Categories

Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

The Challenge

Esan had to pump dirty water from -600 meters at their underground lead-zinc mine, through narrow shafts to upper levels of the mine.

They usually used HDPE and steel pipes but they had clogging problems. This time Esan wanted a pipe that will not clog and will be very easy to install, with no need of fittings installed in the narrow shafts. They tried to find alternatives to prevent leakege problems on the fittings that caused to change them many times.

Pexgol Solution

The client decided to install 350 meters of Pexgol pipe. They choose Pexgol due to it’s experience with providing long pipe sections that enable to avoid installing fittings in narrow shafts and because of the resistance of the pipe to scale build up.

Thanks to Pexgol the installation took just 6 hours, Esan reduced their operation downtime.

Esan built their own decoiler and decoiled the pipe by themselves.

Related Case Studies

Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014