Skip to content

Fiber Optic Cables Through a Vertical Shaft

Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Case Study Nº

99

Customer

Sinohydro
Israel

|

2021

Working Conditions

500 meters hanging without supports inside service shaft

Pexgol Pipes

Pexgol 50 mm (2”) Class 15 | Pexgol 63 mm (2”) Class 15

Application

Fiber Optic Cables Transport

Lenght

Pexgol 50 mm: 14,050 m / 46,095 ft | Pexgol 63 mm: 9,100 m / 29,855 ft

Categories

Installation of Pexgol Pipe to Transport Fiber Optic Cables.

The Challenge

Sinohydro, a Chinese state-owned hydropower engineering and construction company, wanted to install fiber optic cables through a vertical shaft 500 meters deep. They needed conduit pipes that would withstand the tensile forces of the pipe weight. The pipes have to be embedded in concrete, so they have to resist the temperature of the concrete during casting.

Pexgol Solution

Pexgol was chosen due to their ability to withstand high tensile forces and high temperatures.The 63 mm pipe was provided in 13 coils of 700 m each and the 50 mm pipe was provided in 13 coils of 1080 m each.
Only a double mechanical connector was used to hold the pipes above the pit.

Related Case Studies

The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Navigating extreme conditions with Pexgol’s PE-X pipes

Anglo American Perú
Peru

 | 

2023
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Water Transportation through Shafts

Open Cast Mine Dewatering

Agnico Eagle Pinos Altos Mine
Mexico

 | 

2017