Transporting Brine at High Pressure

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Case Study Nº

100

Customer

Mekorot
Israel

|

2020

Working Conditions

Pressure: 36 bar | Flow rate: 120 m^3/hr | Chloride concentration: 10,100 mg/l

Pexgol Pipes

Pexgol 250 mm (10”) Class 43

Application

Brine transport at a Borehole

Lenght

300 m / 984 ft

Categories

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

The Challenge

Mekorot, the national water company of Israel and the country’s top agency for water management, required a corrosion resistant pipe that could hold very high pressure in a deep borehole (300 m). Furthermore, the pipe needed to be able to resist Chloride concentration of 10,100 mg/l.a

Pexgol Solution

A custom-made Pexgol pipe was installed (pipe 250 mm, class 43). The Pexgol pipe was provided in two coils of 150 m each. The two coils were connected by a special coupler that can hold the weight and the high pressure.

The other option that Mekorot considered was a pipe made of super duplex. Since installation of super duplex would take around 3 weeks and cost (approximately) 3,000,000 NIS ($9.3K) while installation of a Pexgol pipe is 3 days and cost about half. Pexgol pipe was the obvious choice.

Related Case Studies

Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
A flexible and durable solution designed to adapt to pit benches, operate outdoors, and minimize connection work in difficult-to-access areas.

Safe Installation of a 355 mm Mine DewateringLine

MMG
Perú

 | 

2024
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023