Hot & Abrasive Potash Brine Processing

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Case Study Nº

87

Customer

Fertilizer Company
Canada

|

2017

Working Conditions

Temperature: 96°C / 204°F

Pexgol Pipes

Pexgol 450 mm (18”), class 24 | Pexgol 400 mm (16”), class 15

Application

Hot Ore and Brine Processing

Lenght

400 m / 1312.34 ft

Categories

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

The Challenge

A Canadian fertilizer company, and the largest producer of potash and the third largest producer of nitrogen fertilizer in the world, required to transport hot ore and brine in their facility in Saskatoon, Saskatchewan.

This was a new intake line. The facility traditionally used FRP and rubber-lined steel pipes. The FRP stress cracking issues and failure mechanism were a concern, and the client wanted to move away from it, but the conditions made material selection challenging.

The new line required to been able to transport saturated chloride brine at elevated temperatures with high resistance to abrasive slurries.

Pexgol Solution

The design of the line was carried out by the engineering company Wood Plc (then AMEC-FW) and Pexgol was selected. Pexgol went through several verification stages to ensure material suitability and verify design parameters:

  • Temperature and pressure suitability.
  • Abrasion resistance comparison with FRP, PP-RCT and other materials.
  • Expansion restraining forces analysis.
  • Support Distance Verification.

The system required a variety of nonstandards elbows, which were made by Golan’s Application Team.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

Related Case Studies

Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Mine Dewatering at Low Temperature

Ferrexpo Yeristovo Mining
Ukraine

 | 

2019
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012