Meltdown Water Transport
Pipe installation on a mountain
Case Study Nº
16
Customer
Codelco Andina, TADA 1-2 Project
Chile
|
2013
Working Conditions
Complex & harsh ground, 300 m altitude.
Pexgol Pipes
Pexgol 315 mm, Class 15 (SDR 11).
Application
Water transportation.
Lenght
3,300 m.
Categories

The Challenge
Codelco needed to transport meltdown water downhill at Andes Mountain range.
The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.
Pexgol Solution
Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.
The installation was simplified by the use of Pexgol long sections.
The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.
The installation was done in perfect timing with an optimal performance.
Related Case Studies
Transport of Silica Arena: HDPE vs Pexgol
Covia Corp
Mexico
|
2019
Fast and Reliable Solution for Winemaking Processes
Zuccardi Winery
Argentina
|
2024
Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant
Kimex
Mexico
|
2025
High Corrosion Resistance Against Brine
Unipar Carbocloro
Brazil
|
2019
Streamlining Water Supply in Highway Construction
Chediack / Ceosa
Argentina
|
2023