Transport of Muddy Water in a Palm Oil Processing Plant

Transport of Muddy Water (Pome) witha High Content of Organic Load.

Case Study Nº

85

Customer

La Gloria
Colombia

|

2020

Working Conditions

Temperature: 80°C | Flow: 36m³/h

Pexgol Pipes

Pexgol 110 mm (4″), clase 12

Application

Muddy water transportation

Lenght

1200 m

Categories

Transport of Muddy Water (Pome) witha High Content of Organic Load.

The Challenge

La Gloria, a company dedicated to the extraction of palm oil in César (Colombia), required a new line to transport muddy water to the oxidation ponds. From the florentino lagoon (treatment pool), passing through the main road and the plantation, the excavation and installation of the pipe had to be carried out in the crop, between palms without causing damage to the plants and the irrigation pipe. In addition, given the operating conditions and the type of fluid, a pipe was required that resists high temperatures and has a low internal roughness index due to incrustations.

Pexgol Solution

Due to the high costs of carbon steel pipe, added to the cost of assembly, it was decided to use Pexgol pipes.

Pexgol was selected for its quick and easy installation, fewer joints and the possibility of supplying it in rolls.

The installation of the 1200 meters was carried out in 4 hours. Four electrofusion joints were used for the splicing of the sections and a mechanical joint was used at each end.

Related Case Studies

Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017