Skip to content

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Transformation in the logistics of formation water.

Case Study Nº

158

Customer

Aconcagua Energía
Argentina

|

2023

Working Conditions

Temperature: 35°C / 95°F | Flow: 80 m³/h | Pressure: 10 kg/m

Pexgol Pipes

Pexgol 90 mm class 15 & 110 mm class 24

Application

Injection water transport

Lenght

10,000 m / 32808.4 ft

Categories

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

The Challenge

Aconcagua Energía, a prominent independent energy company in Argentina, faced significant challenges in transporting injection water, crucial for its oil operations. Traditionally, formation water was transported by trucks from the treatment plant to the elevated tanks, which not only represented a high operational cost but also involved risks associated with transport and logistical difficulties, especially during adverse weather conditions or certain times of the year. The need for a more efficient, safe, and economical solution was evident.

The Solution

In search of improving operational efficiency and reducing costs, Aconcagua Energía opted for the implementation of an innovative pipeline using 90 and 110 mm Pexgol for a total of 10,000 meters. The choice of Pexgol was due to its recognized advantages in terms of installation speed, material flexibility, lightness and ease of handling, as well as the ability to transport in rolls, which greatly simplified logistics on the ground.
The installation was carried out in stages, minimizing assembly times and optimizing the resources used. Mechanical double connectors and flanged couplings were used, facilitating a safe and efficient integration into the existing system.

The project not only eliminated the dependency on truck transportation but also brought tangible benefits in terms of operational costs and associated risks. The first phase of the installation included the assistance and training of Argpex in unrolling techniques and the use of mechanical connectors. For the later stages, the Aconcagua Energía team was able to carry out the installation autonomously, demonstrating the effectiveness and ease of implementation of the Pexgol system.

Related Case Studies

Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010