Skip to content

Streamlining Water Supply in Highway Construction

Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Case Study Nº

135

Customer

Chediack / Ceosa
Argentina

|

2023

Working Conditions

Pexgol Pipes

Pexgol 160 mm, Class 15

Application

Water network

Lenght

188 m / 616 ft

Categories

Streamlining Water Supply in Highway Construction

The Challenge

The construction companies Chediack and Ceosa are undertaking a significant project in Argentina – building a dual-track highway that connects Mendoza to San Juan. As they embarked on the construction of the second section, they faced a specific challenge. They had to provide water to the cooperative responsible for the water distribution in that sector while constructing the highway. This required running a pipeline underneath the highway. The existing pipeline system, made of rubber and PVC, presented an interference under the embankment of the highway.

Furthermore, the challenge was compounded by the need to use a material that allowed for a continuous pipeline without dependencies on joints, given the considerable length of 188 meters (about 616 feet).

Pexgol Solution

Pexgol offered an apt solution to Chediack and Ceosa’s unique challenge with their 160mm PE-X pipe. Pexgol’s pipeline, owing to its ability to be shipped in long coils, allowed for a full-length installation without the need for joints. This attribute turned out to be particularly beneficial given the significant length required for this project.
Loose flanges and MAS joints were used in the installation process, which was quick and efficient. Once the trenching was completed, the Pexgol pipe was transported to the site, unrolled, lowered, and distributed into the trench. The trench was then backfilled with the excavated soil, compacted, and the remaining cover and compaction completed. The consortium responsible handled the connections to
the existing network and subsequent commissioning.

Opting for Pexgol’s pipeline system provided a multitude of benefits. Its quick installation time, lightweight and easy-to-handle properties, ability to provide long sections, and transportation in rolls helped streamline the water supply infrastructure in the highway construction project. The practicality and efficiency of Pexgol’s pipeline solution made it a valuable resource in the construction of the highway between Mendoza and San Juan.

Related Case Studies

Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Replacement of Carbon Steel Pipe for a Pexgol Pipe

Water Transportation

Cargill
Mexico

 | 

2017