Skip to content

Addressing Drainage Challenges with Pexgol

Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Case Study Nº

149

Customer

Avino Mine
Mexico

|

2023

Working Conditions

Temperature: 21°C / 69°F | Flow: 400 USGPM | Pressure: 400 psi | Fluid Components: Water

Pexgol Pipes

Pexgol 6″, SDR 11 & 6″, SDR 6

Application

Mine Dewatering

Lenght

720 m / 2372 ft

Categories

Addressing Drainage Challenges with Pexgol

The Challenge

Minera Mexicana de Avino, with its vast gold and silver production operations near Durango, Mexico, faced a significant challenge. The company had been relying on HDPE piping for mine drainage. However, issues with pipe joints began to arise, which prompted the search for a more reliable and effective alternative. With a strategic focus on the acquisition of advanced exploration and mining properties, and a commitment to environmentally responsible operations, a durable and efficient drainage solution was critical.

Pexgol Solution

Recognizing the challenges, Pexgol provided a robust solution with its 480 meters of 6-inch SDR6 piping (2 coils) and 240 meters of 6-inch SDR11 piping (1 coil). These were employed across three separate lines, each measuring 240 meters (787.4 feet).
Pexgol’s unique attributes, such as rapid installation, long lifespan, and extended pipe lengths, directly addressed the challenges posed by the existing HDPE pipes.

The piping was installed in a ventilation duct where the ambient temperature ranges between 40° and 60°C (104° and 140°F), allowing the client to achieve substantial savings. Without installing the piping through the ventilation duct, they would have had to make a special borehole or install it via a ramp.

The installation was meticulously planned, especially since the existing path presented various challenges, including proximity to a fiber optic cable and the transit of machinery. With careful coordination, the installation was swiftly achieved, impressing the client with the speed and efficiency of the maneuver. The use of flanged couplings and load clamps ensured a secure and sturdy connection.

The feedback from Avino was overwhelmingly positive, expressing surprise and satisfaction at the rapidity of the maneuvering and installation process, reinforcing the benefits of choosing Pexgol.

Related Case Studies

Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Nexa Resources
Brazil

 | 

2023
Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015
Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023