Skip to content

Addressing Drainage Challenges with Pexgol

Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Case Study Nº

149

Customer

Avino Mine
Mexico

|

2023

Working Conditions

Temperature: 21°C / 69°F | Flow: 400 USGPM | Pressure: 400 psi | Fluid Components: Water

Pexgol Pipes

Pexgol 6″, SDR 11 & 6″, SDR 6

Application

Mine Dewatering

Lenght

720 m / 2372 ft

Categories

Addressing Drainage Challenges with Pexgol

The Challenge

Minera Mexicana de Avino, with its vast gold and silver production operations near Durango, Mexico, faced a significant challenge. The company had been relying on HDPE piping for mine drainage. However, issues with pipe joints began to arise, which prompted the search for a more reliable and effective alternative. With a strategic focus on the acquisition of advanced exploration and mining properties, and a commitment to environmentally responsible operations, a durable and efficient drainage solution was critical.

Pexgol Solution

Recognizing the challenges, Pexgol provided a robust solution with its 480 meters of 6-inch SDR6 piping (2 coils) and 240 meters of 6-inch SDR11 piping (1 coil). These were employed across three separate lines, each measuring 240 meters (787.4 feet).
Pexgol’s unique attributes, such as rapid installation, long lifespan, and extended pipe lengths, directly addressed the challenges posed by the existing HDPE pipes.

The piping was installed in a ventilation duct where the ambient temperature ranges between 40° and 60°C (104° and 140°F), allowing the client to achieve substantial savings. Without installing the piping through the ventilation duct, they would have had to make a special borehole or install it via a ramp.

The installation was meticulously planned, especially since the existing path presented various challenges, including proximity to a fiber optic cable and the transit of machinery. With careful coordination, the installation was swiftly achieved, impressing the client with the speed and efficiency of the maneuver. The use of flanged couplings and load clamps ensured a secure and sturdy connection.

The feedback from Avino was overwhelmingly positive, expressing surprise and satisfaction at the rapidity of the maneuvering and installation process, reinforcing the benefits of choosing Pexgol.

Related Case Studies

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019