Case Study Nº

171

Customer

Lithos (PAE)
Argentina

|

2024

Working Conditions

Temperature: 20°C / 58°F | Flow rate: 80.3 m³/h | Pressure: 8.6 bar | Fluid: Brine

Pexgol Pipes

Pexgol 160 mm (6″) class 10

Application

Brine transport

Lenght

10,000 m / 32808.4 ft

Categories

Fast and Safe Brine Transport in the Salar de Hombre Muerto

The Challenge

Pan American Energy, a leader in oil, gas, and renewable energy exploration and production, faced a logistical challenge during the performance testing phase of its lithium mining project (Lithos) in the Salar de Hombre Muerto, Argentina. The company needed a reliable and flexible transport line for brine transfer between pumping wells, in a demanding salt flat environment.

The project called for a solution capable of withstanding abrasive terrain, enduring constant movement between wells, and ensuring pipeline integrity throughout the process. At the same time, Pan American Energy aimed to reduce operational costs and minimize environmental impact, in line with its sustainability objectives.

The Solution

To meet these challenges, Pan American Energy installed 10 kilometers of 6-inch Pexgol pipes in 450-meter coils. This solution proved ideal due to the following advantages:

  • Quick Installation: Each 450-meter coil was deployed in just 15 minutes, significantly reducing installation time and enabling quick movement between wells.
  • High Chemical and Abrasion Resistance: Pexgol pipes withstood the abrasive terrain and extreme weather conditions of the Salar de Hombre Muerto, ensuring uninterrupted operation without damage.
  • Long Sections: The use of long-length coils minimized the number of joints required, reducing potential failure points and improving pipeline safety.

The operation was highly efficient: each well was tested for a set duration, and afterward, the same pipe was dragged to the next well, eliminating the need for multiple lines. This method allowed Pan American Energy to optimize resources, lower costs, and speed up its testing schedule.

Related Case Studies

Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021