Skip to content

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Pan American Energy implements an efficient and sustainable solution for brine transportation.

Case Study Nº

171

Customer

Lithos (PAE)
Argentina

|

2024

Working Conditions

Temperature: 20°C / 58°F | Flow rate: 80.3 m³/h | Pressure: 8.6 bar | Fluid: Brine

Pexgol Pipes

Pexgol 160 mm (6″) class 10

Application

Brine transport

Lenght

10,000 m / 32808.4 ft

Categories

Fast and Safe Brine Transport in the Salar de Hombre Muerto

The Challenge

Pan American Energy, a leader in oil, gas, and renewable energy exploration and production, faced a logistical challenge during the performance testing phase of its lithium mining project (Lithos) in the Salar de Hombre Muerto, Argentina. The company needed a reliable and flexible transport line for brine transfer between pumping wells, in a demanding salt flat environment.

The project called for a solution capable of withstanding abrasive terrain, enduring constant movement between wells, and ensuring pipeline integrity throughout the process. At the same time, Pan American Energy aimed to reduce operational costs and minimize environmental impact, in line with its sustainability objectives.

The Solution

To meet these challenges, Pan American Energy installed 10 kilometers of 6-inch Pexgol pipes in 450-meter coils. This solution proved ideal due to the following advantages:

  • Quick Installation: Each 450-meter coil was deployed in just 15 minutes, significantly reducing installation time and enabling quick movement between wells.
  • High Chemical and Abrasion Resistance: Pexgol pipes withstood the abrasive terrain and extreme weather conditions of the Salar de Hombre Muerto, ensuring uninterrupted operation without damage.
  • Long Sections: The use of long-length coils minimized the number of joints required, reducing potential failure points and improving pipeline safety.

The operation was highly efficient: each well was tested for a set duration, and afterward, the same pipe was dragged to the next well, eliminating the need for multiple lines. This method allowed Pan American Energy to optimize resources, lower costs, and speed up its testing schedule.

Related Case Studies

The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
Transforming water transportation with Pexgol technology

Pexgol’s Solution for CFE: A Leap in Durability and Efficiency

Comisión Federal de Electricidad
Mexico

 | 

2023
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Optimization of Water Systems in the Energy Industry.

“Threading” Pexgol Pipes

Pluspetrol
Argentina

 | 

2023
Pexgol extends pipe lifespan and reduces maintenance in salt production.

Fewer Shutdowns, Greater Efficiency: Pexgol in the Salt Industry

Sales del Istmo
Mexico

 | 

2023