High Pressure Water Transport

High Pressure Water Transport for a Gold Mine.

Case Study Nº

86

Customer

Mansfield Mine
Argentina

|

2019

Working Conditions

Exposed pipe with repump systems at 21 bar (305 PSI)

Pexgol Pipes

Pexgol 225 mm (8″), class 24, 19, 15 & 12

Application

Water transport

Lenght

12.5 km

Categories

High Pressure Water Transport for a Gold Mine.

The Challenge

The engineering company SAXUM had the challenge of designing the main water supply line for Mansfield’s “Lindero Gold Mine” project, which through heap leaching removes and processes mineral.

Given the differences in height (more than 300 meters in total) and the length, a pipe was required that would provide safety to work with high pressures and that can be exposed to the sun without the need to bury it.

Due to the climatic conditions of the area, with low temperatures and strong winds, added to the height (above 4000 m above sea level), a simple and quick solution to install was sought, since otherwise the costs of assembly would be very high.

Pexgol Solution

It was decided to install Pexgol since it is supplied in coils, in this case up to 280 meters in length. Compared to steel and HDPE supplied in 12 or 14 meter lengths, this supply format kept labor and the posibility of failure to a minimum.

Approximately 1,400 meters were installed per day with only three operators and a backhoe. The connections were made by electrofusion couplings.

Related Case Studies

Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010