Skip to content

Mineral Processing – Brine Transportation

Reduction of material build-up in brine and brine/acid lines

Case Study Nº

8

Customer

SQM,Pedro Valvidia Mine
Chile

|

2010

Working Conditions

Ambient temperature -5°C to 0°C (32°F to 23°F). High level of material build-up and corrosion inside the pipe. Working pressure: 15 bar.

Pexgol Pipes

Pexgol and elbows 160×14.6, Class 15.

Application

Brine and acid transportation.

Lenght

12 meters.

Categories

Mineral Processing - Brine Transportation

The Challenge

As the brine water and acid solution was being transported by the initial HDPE pipeline, salts were sticking to the pipe walls, reducing the inner diameter. Due to the low ambient temperatures, deposits of calcium sulfate formed on the inner wall of the pipes and on the elbows.

The matter was critical since the problem forced complete halting of work at the plant as well as lot of maintenance and reduction of production capacity.

Pexgol Solution

SQM decided to replace its HDPE pipes and elbows with Pexgol’s. Due to the especially smooth internal surface of Pexgol’s pipes and elbows, the replacement of HDPE pipes with Pexgol eliminated the problem of chemical deposits. This resulted in fewer work interruptions and improved production capacity.

The production and transportation of Pexgol’s pipes in coils also reduces the number of joints and possibility of clogging. As a result, it reduced maintenance costs and brought the end of frequent forced halts in the work processes at the plant.

The original mean time between failures (MTBF) of the HDPE pipes was one month. Since changing to Pexgol in 2010, no sign of failure has been detected.

Related Case Studies

Extraction of underground water through wells

Extraction of Underground Water

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2010
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Mine Dewatering at Low Temperature

Ferrexpo Yeristovo Mining
Ukraine

 | 

2019
Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017