Overcoming Installation Hurdles and Enhancing Operational Efficiency

Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Case Study Nº

134

Customer

Newmont
Argentina

|

2022

Working Conditions

Underground Mine

Pexgol Pipes

Pexgol 63, 180, 225, 250 & 250 mm, Class 15

Application

Mine Dewatering

Lenght

1100 m / 3608 ft

Categories

Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

The Challenge

Newmont Corporation, an American gold mining company and the world’s largest gold mining corporation, owns mines in various locations worldwide, including their Cerro Negro mine located in Santa Cruz, Argentina. The mining process requires robust and efficient infrastructure, and for Newmont, the pipeline system was presenting a significant challenge.

The mine needed to add dewatering lines, they previously used High-Density Polyethylene (HDPE) for their service lines, which resulted in logistical and operational problems. HDPE pipes are typically produced in lengths of 12 meters, necessitating a high degree of manipulation during installation. This was particularly challenging in a mining environment, where efficiency and safety are paramount.

Furthermore, the rigid nature of HDPE piping limited its application in environments with complex terrain and demanding conditions, typical of mining operations.

Pexgol Solution

Recognizing the limitations of HDPE and the need for a superior solution, Newmont Corporation turned to Pexgol – a PE-X pipe renowned for its durability, flexibility, and ease of installation.

Pexgol 160mm class 30, 110mm class 24, and 110mm class 30 pipes were used, extending over 1100 meters for underground mine dewatering and water transportation. The pipes were installed using double mechanical connectors and Victaulic fittings, ensuring a secure and leak-free connection.

The installation process was significantly streamlined due to the advantageous properties of Pexgol. An impressive 500 meters of pipeline were installed in just 5 hours, a testament to the efficiency of the product. Pexgol’s long lengths and lightweight properties allowed the pipe to be quickly deployed down a ramp and subsequently hung in place.

Related Case Studies

Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Sewage Water Transportation with 300 PPM Hydrogen Peroxide

Sewage Water Transportation

BorsodChem
Hungary

 | 

2011