Working Conditions

Temperature: 98°C / 210°F | Pressure: 130 psi

Pexgol Pipes

Pexgol 9″ & 14″

Application

District Energy Network

Lenght

Significant

Categories

Scaling Up Efficiency: District Energy at Penn State Harrisburg

The Challenge

Penn State University Harrisburg required a reliable and efficient solution for its High-Temperature Hot Water Supply & Return (HT-HWS&R) system. The university needed a durable piping system capable of withstanding continuous high temperatures of 210°F at 130 psi while ensuring long-term performance with minimal maintenance. The solution had to be implemented underground, with direct burial, making resistance to environmental and operational stress a key requirement.

The project was executed in two phases, with Phase 1 completed in 2021 and an expansion (Phase 2) successfully implemented in 2023. With the growing infrastructure needs of the campus, further installations are anticipated in the future.

The Solution

For Phase 1 of the project, the university selected Pexgol 225 mm (9” Nom.) SDR 6 piping. The pipes were supplied in coils, allowing for efficient installation with minimal joints. The system was buried directly, with field-applied closed-cell spray foam insulation to ensure energy efficiency and temperature retention. Since its commissioning in 2021, the system has provided reliable service.

Following the success of Phase 1, Phase 2 was initiated in 2023, incorporating larger Pexgol 355mm (14” Nom.) and 225mm (9” Nom.) SDR 6 pipes. Like the first phase, the pipes were delivered in coils for direct burial, reducing installation time and costs while maintaining the same high-temperature and pressure resistance. The field-applied spray foam insulation continued to enhance thermal efficiency.

Penn State Harrisburg continues to expand its district energy network with Pexgol solutions, with additional phases expected in the near future. This project showcases Pexgol’s ability to meet demanding, long-term district heating requirements with efficiency, reliability, and cost-effectiveness.

Related Case Studies

The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022
Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015
Replacement of Carbon Steel Pipe for a Pexgol Pipe

Water Transportation

Cargill
Mexico

 | 

2017
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide