Water Transport with Low pH Level

Transport of acid water at high temperatures

Case Study Nº

2

Customer

Moa Nickel S.A. Sherritt
Cuba

|

2010

Working Conditions

Up to 65°C, 13 bars.

Pexgol Pipes

Pexgol 225 mm, Class 24 (SDR 7.3).

Application

Transportation of Acid Water.

Lenght

2500 m.

Categories

Level pH Low with Transport Water

The Challenge

Moa Nickel required to transport a big amount of overflow acid water from the sedimentation tanks to the slurry thickeners plant.

This overflow water substituted the reposition water that the slurry thickeners used.

The client debated regarding the use of a stainless steel pipe SS316L or thermoplastic flexible materials such as HDPE and polyethylene.

Pexgol Solution

At the end, Moa Nickel decided to use Pexgol pipes in long sections, instead of short ones of HDPE and polyethylene, as the best solution for the line, because this type of materials didn’t allow to work under the security standards in the allowable installation time.

The Pexgol pipe was installed in just 8 days with success. The fact that it didn’t require to create a sand bed and the high productivity for its installation in long sections, reduced to the half the installation time for this project. At the end, the client got 25% savings in comparison with the other possible materials.

Related Case Studies

Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016
Optimization of Water Systems in the Energy Industry.

“Threading” Pexgol Pipes

Pluspetrol
Argentina

 | 

2023
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 