Adiós al Asbesto: Pexgol moderniza red de agua termal

850 metros de tubería reemplazados en menos de 24 horas, sin afectar a los residentes.

Caso de Estudio Nº

180

Cliente

Raquet Club Lake Chapala
México

|

2024

Condiciones Operativas:

Temperatura: 87°C / 188°F | Caudal: 15 l/s | Presion: 9.9 bar | Componentes del fluido: Agua termal (con concentraciones de cloruros, sulfatos, sodio, calcio y magnesio)

Tuberías Utilizadas:

Pexgol 6” SDR 7.3, SDR 11 y SDR 15

Uso:

Transporte de aguas termales

Largo:

850 m / 2788.71 ft

Categorías:

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

El Desafío

El Raquet Club Lake Chapala, un club de tenis ubicado en San Juan Cosalá (México), contaba con una red de conducción de aguas termales construida con tuberías de asbesto cemento de 10”, instaladas hace varias décadas. Si bien este tipo de material era considerado resistente en su época, hoy se reconoce su peligrosidad: las fibras de asbesto pueden liberarse al deteriorarse las tuberías, representando un riesgo grave para la salud de los residentes.

El fraccionamiento enfrentaba un dilema. Reemplazar la línea existente con soluciones convencionales implicaba cortes prolongados del suministro de agua potable, un impacto inaceptable para los usuarios. Además, las alternativas disponibles no garantizaban resistencia suficiente frente a los desafíos de esta red: alta temperatura (87°C), presión de 9.9 bar y composición química agresiva (bicarbonatos, cloruros, sulfatos, calcio, magnesio, sodio).

Las opciones tradicionales también requerían excavaciones extensas para retirar las antiguas tuberías, encareciendo y alargando la intervención. El deterioro estructural del asbesto cemento, combinado con los riesgos sanitarios y operativos, hacía urgente una solución innovadora, eficiente y segura.

Solución Pexgol

The choice of Pexgol pipes for this renovation was key to overcoming all project challenges. A total of 850 linear meters were installed in different pressure classes (SDR 7.3, SDR 11, and SDR 15) in just one working day, meeting the commitment to keep water supply interruptions under 24 hours.

How was this achieved? By using the existing asbestos pipe as a guiding duct, the new Pexgol line was pulled through the entire route with a steel cable, eliminating the need for excavations. Thanks to its abrasion resistance and high flexibility, Pexgol withstood the pulling process without compromising its integrity. In addition, its ultra-smooth inner surface (roughness 0.0006 mm) allowed maintaining the original flow rate despite the pipe’s smaller internal diameter, optimizing hydraulic performance.

The installation was carried out using flanged couplings, without welding or complex works. Although the contractor had no prior experience with this system, Pexgol’s technical team provided full support: maneuver selection, staff training, and detailed planning. The result was a fast, clean, and safe implementation—without causing inconvenience to residents.

Casos de Estudio Relacionados

Instalación de un Sistema de Drenaje entre Tranques en una Mina de Cobre.

Transporte de Agua entre Tranques

CODELCO – Mina El Teniente
Chile

 | 

2019
Transporte de Aguas Grises para Reciclaje

Transporte de Agua Recuperada

Coeur Mexicana S.A. de C.V. Palmarejo
México

 | 

2017
Desagüe de Tajo en Terreno Dificultoso

Desagüe de Tajo

Timmins Gold Corp Group, Minera Molimentales del Noroeste
México

 | 

2016
Transporte de agua a alta presión para tajo sur en minera de cobre y zinc.

Dewatering a Alta Presión

Minera Antapaccay
Perú

 | 

2023
Transporte de Agua de Formación con Hidrocarburos.

Transporte de Agua de Formación

ROCH
Argentina

 | 

2015
Instalación de Tubería Pexgol en Planta de Tratamiento de Agua de Formación.

Planta de Agua de Inyección Secundaria

YPF
Argentina

 | 

2020