Skip to content

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Estudo de Caso Nº

180

Cliente

Raquet Club Lake Chapala
Mexico

|

2024

Condições de Trabalho

Temperature: 87°C / 188°F | Flow Rate: 15 l/s | Pressure: 9.9 bar | Fluid Components: Thermal water (with chlorides, sulfates, sodium, calcium, and magnesium)

Solução Pexgol

Pexgol 6” SDR 7.3, SDR 11 & SDR 15

Aplicação

Thermal water transportation

Comprimento

850 m / 2788.71 ft

Categorias

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

The Challenge

Raquet Club Lake Chapala, a tennis club located in San Juan Cosalá (Mexico), had a thermal water distribution network built with 10” asbestos cement pipes installed several decades ago. Although this material was considered durable at the time, it is now recognized as hazardous: asbestos fibers can be released as pipes deteriorate, posing a serious health risk to residents.

The community faced a dilemma. Replacing the existing line with conventional solutions would involve prolonged interruptions to the potable water supply— an unacceptable impact for users. Additionally, the available alternatives could not guarantee sufficient resistance to the network’s demanding conditions: high temperature (87°C), pressure of 9.9 bar, and aggressive chemical composition (bicarbonates, chlorides, sulfates, calcium, magnesium, sodium).

Traditional options also required extensive excavation to remove the old pipes, significantly increasing costs and extending the project timeline. The structural deterioration of asbestos cement, combined with health and operational risks, made an innovative, efficient, and safe solution urgently necessary.

The Solution

The choice of Pexgol pipes for this renovation was key to overcoming all project challenges. A total of 850 linear meters were installed in different pressure classes (SDR 7.3, SDR 11, and SDR 15) in just one working day, meeting the commitment to keep water supply interruptions under 24 hours.

How was this achieved? By using the existing asbestos pipe as a guiding duct, the new Pexgol line was pulled through the entire route with a steel cable, eliminating the need for excavations. Thanks to its abrasion resistance and high flexibility, Pexgol withstood the pulling process without compromising its integrity. In addition, its ultra-smooth inner surface (roughness 0.0006 mm) allowed maintaining the original flow rate despite the pipe’s smaller internal diameter, optimizing hydraulic performance.

The installation was carried out using flanged couplings, without welding or complex works. Although the contractor had no prior experience with this system, Pexgol’s technical team provided full support: maneuver selection, staff training, and detailed planning. The result was a fast, clean, and safe implementation—without causing inconvenience to residents.

Estudos de Caso Relacionados

Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categorias:

Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Greater operational efficiency with fewer joints and fast implementation.

Fresh Water Line Optimization in an Oil Field in Argentina

Phoenix Global Resources
Argentina

 | 

2025