Overcoming Geotechnical Challenges with Pexgol at Media Luna

Improving drainage in the Media Luna mine with Pexgol.

Caso de Estudio Nº

159

Cliente

Minera Media Luna
Mexico

|

2023

Condiciones Operativas:

Temperature: 25°C / 77°F | Flow: 80 l/sec | Pressure: 28.5 bar

Tuberías Utilizadas:

Pexgol 8″ SDR 6

Uso:

Mine Dewatering

Largo:

540 m / 1640.42 ft

Categorías:

Overcoming Geotechnical Challenges with Pexgol at Media Luna

The Challenge

Torex Gold, an intermediate gold producer with operations in the Guerrero gold belt in Mexico, faced a significant challenge at its Media Luna mine. The need for an effective underground water pumping system was critical to continuing mining operations. The conventional alternative of using steel pipes presented multiple disadvantages, including the high cost of installation and materials, the need for frequent welding every 12 meters, and the requirement for specialized machinery for installation inside the mine, in addition to susceptibility to corrosion due to high humidity in the underground environment.

The Solution

After a thorough analysis, Torex Gold selected 8” SDR 6 Pexgol pipes for a total of 540 metres distributed in two coils of 270 metres each. Pexgol pipes were chosen for their corrosion resistance, the possibility of supplying them in long sections that significantly reduce joints, and their fast and efficient installation. In addition, the lightness and flexibility of the material facilitated its handling and installation in the complex mine environment.
The implementation of the Pexgol solution at Minera Media Luna not only met the operational and technical requirements of the project, but also exceeded expectations in terms of installation efficiency and costs. The ability to supply pipes in long coils allowed for continuous installation without the interruptions and costs associated with welding required by steel pipes. In addition, the mine’s in-house engineering successfully designed the surface base and the clamping platform at the end of the countershaft, ensuring seamless integration of the Pexgol system into the existing infrastructure. This project not only demonstrated the technical and economic viability of Pexgol pipes in challenging mining applications, but also set a precedent for future implementations, highlighting the importance of selecting innovative materials that offer durable and cost-effective solutions in the mining industry.

Casos de Estudio Relacionados

Pexgol: Brindando soluciones rápidas, fiables y duraderas para el drenaje minero.

Abordando los Desafíos del Dewatering con Pexgol

Avino Mine
México

 | 

2023
Transporte de sedimentos de salmuera cristalizada (a una concentración del 30%)

Transporte de Cristales de Salmuera

ICL Group, Mar Muerto
Israel

 | 

1992
Reducción del desgaste y aumento de la durabilidad en el proceso de limpieza de arena en KSB de México.

Mejorando la Eficiencia en la Fundición de Acero con Pexgol

KSB de Mexico
México

 | 

2023
Reemplazo de Tubería HDPE por Pexgol

Transporte de Jales

Mina Tizapa Zacasonapa
México

 | 

2015
Tendido de Tubería sobre la Montaña

Transporte de Agua de Deshielo

Codelco Andina, Proyecto TADA 1-2
Chile

 | 

2013
Tuberías Pexgol: Resolviendo desafíos de instalación, manejo y flexibilidad en la Mina Cerro Negro

Agilizando el desagüe y transporte de agua con las tuberías Pexgol

Newmont
Argentina

 | 

2022