Solución Integral para Transporte de Agua en Proyectos Urgentes

Cómo Pexgol aceleró el suministro y la instalación de una línea crítica en Madagascar.

Caso de Estudio Nº

170

Cliente

Madagascar Mining
Madagascar

|

2024

Condiciones Operativas:

Temperatura: 25°C / 77°F | Caudal: 300 m³/h | Presión: 28 bar | Componentes del fluido: Arena

Tuberías Utilizadas:

Pexgol 280 mm (10″) clases 30, 24, 19 y 15

Uso:

Transporte de agua de río

Largo:

6 km

Categorías:

Comprehensive Water Transportation Solution for Urgent Projects

Solución Pexgol

Pexgol proporcionó una solución ideal para este proyecto mediante el suministro de tuberías de 280 mm (10”) en clases 30, 24, 19 y 15. Estas tuberías fueron seleccionadas debido a su capacidad para manejar altas presiones, su flexibilidad, y su facilidad de instalación. Además, se suministraron en rollos largos de 100, 200 y 300 metros, lo que permitió reducir significativamente la cantidad de conexiones necesarias.

El sistema de accesorios utilizado incluyó coplas de electrofusión, flared ends y bridas sueltas, garantizando conexiones seguras y rápidas. La asistencia técnica de Pexgol incluyó soporte desde la etapa de diseño hasta la instalación en campo, con capacitación y herramientas suministradas para optimizar el proceso.

La Minera evaluó alternativas como tuberías flexibles de acero con recubrimientos de PE, pero estas opciones fueron descartadas debido a los tiempos de entrega prolongados y la necesidad de herramientas especializadas para la instalación.

Pexgol demostró ser la solución más eficiente y viable, ofreciendo una respuesta rápida y adaptada a las necesidades del cliente.

La experiencia con Pexgol en este proyecto subraya su capacidad para superar
desafíos técnicos y logísticos en condiciones exigentes.

The Solution

Pexgol provided an ideal solution for this project by supplying 280 mm (10”) pipes in classes 30, 24, 19, and 15. These pipes were selected due to their ability to handle high pressures, flexibility, and ease of installation. Additionally, they were supplied in long coils of 100, 200, and 300 meters, which significantly reduced the number of required connections.

The fitting system used included electrofusion couplings, flared ends, and loose flanges, ensuring secure and quick connections. Pexgol’s technical support covered the entire process, from design to on-site installation, including training and tools to optimize the project’s execution.

Ambatovy evaluated alternative solutions such as steel flexible pipes with PE coatings but ruled them out due to long delivery times and the need for specialized installation tools. Pexgol proved to be the most efficient and viable solution, providing a fast, tailored response to the client’s needs.

Pexgol’s performance in this project highlights its ability to overcome technical and logistical challenges in demanding conditions.

Casos de Estudio Relacionados

El papel de Pexgol en la mejora de las operaciones de Guaymas Protein.

Transición a Sistemas de Entrega de Diésel Libres de Corrosión

Guaymas Protein
México

 | 

2023
Tuberías Pexgol: Resolviendo desafíos de instalación, manejo y flexibilidad en la Mina Cerro Negro

Agilizando el desagüe y transporte de agua con las tuberías Pexgol

Newmont
Argentina

 | 

2022
Solución rápida y confiable para procesos vitivinícolas

Solución Rápida y Confiable para Procesos Vitivinícolas

Bodega Zuccardi
Argentina

 | 

2024
Desagüe de Tajo en Terreno Dificultoso

Desagüe de Tajo

Timmins Gold Corp Group, Minera Molimentales del Noroeste
México

 | 

2016
Transporte de Agua Excedente de Lluvia en una Mina

Desagüe de Tajo Minero

Mina El Volcan Arcelor Mittal
México

 | 

2017
Instalación de Tubería Pexgol para Transporte de Relave Minero.

Transporte de Relaves con 50% de Sólidos

Golden Resource Corp. – Mina Don David Gold
México

 | 

2019