Caso de Estudio Nº

170

Cliente

Madagascar Mining
Madagascar

|

2024

Condiciones Operativas:

Temperatura: 25°C / 77°F | Caudal: 300 m³/h | Presión: 28 bar | Componentes del fluido: Arena

Tuberías Utilizadas:

Pexgol 280 mm (10″) clases 30, 24, 19 y 15

Uso:

Transporte de agua de río

Largo:

6 km

Categorías:

Comprehensive Water Transportation Solution for Urgent Projects

Solución Pexgol

Pexgol proporcionó una solución ideal para este proyecto mediante el suministro de tuberías de 280 mm (10”) en clases 30, 24, 19 y 15. Estas tuberías fueron seleccionadas debido a su capacidad para manejar altas presiones, su flexibilidad, y su facilidad de instalación. Además, se suministraron en rollos largos de 100, 200 y 300 metros, lo que permitió reducir significativamente la cantidad de conexiones necesarias.

El sistema de accesorios utilizado incluyó coplas de electrofusión, flared ends y bridas sueltas, garantizando conexiones seguras y rápidas. La asistencia técnica de Pexgol incluyó soporte desde la etapa de diseño hasta la instalación en campo, con capacitación y herramientas suministradas para optimizar el proceso.

La Minera evaluó alternativas como tuberías flexibles de acero con recubrimientos de PE, pero estas opciones fueron descartadas debido a los tiempos de entrega prolongados y la necesidad de herramientas especializadas para la instalación.

Pexgol demostró ser la solución más eficiente y viable, ofreciendo una respuesta rápida y adaptada a las necesidades del cliente.

La experiencia con Pexgol en este proyecto subraya su capacidad para superar
desafíos técnicos y logísticos en condiciones exigentes.

The Solution

Pexgol provided an ideal solution for this project by supplying 280 mm (10”) pipes in classes 30, 24, 19, and 15. These pipes were selected due to their ability to handle high pressures, flexibility, and ease of installation. Additionally, they were supplied in long coils of 100, 200, and 300 meters, which significantly reduced the number of required connections.

The fitting system used included electrofusion couplings, flared ends, and loose flanges, ensuring secure and quick connections. Pexgol’s technical support covered the entire process, from design to on-site installation, including training and tools to optimize the project’s execution.

Ambatovy evaluated alternative solutions such as steel flexible pipes with PE coatings but ruled them out due to long delivery times and the need for specialized installation tools. Pexgol proved to be the most efficient and viable solution, providing a fast, tailored response to the client’s needs.

Pexgol’s performance in this project highlights its ability to overcome technical and logistical challenges in demanding conditions.

Casos de Estudio Relacionados

Transporte de agua lodosa (POME) con alto contenido de carga orgánica.

Transporte de Agua Lodosa en Planta Procesadora de Aceite de Palma

La Gloria
Colombia

 | 

2020
Prueba Comparativa para el Transporte de Salmuera con Tuberías de HDPE y Pexgol.

Comparativa en Transporte de Salmuera

Albemarle Salar
Chile

 | 

2020
Optimización de sistemas de acueductos en la industria energética.

“Enhebrando” Tuberías Pexgol

Pluspetrol
Argentina

 | 

2023
El impacto de las tuberías Pexgol en la mejora del rendimiento de la bomba y la reducción \de costos de mantenimiento en Sales de Jujuy.

Mejora en la gestión de salmuera a través de tuberías Pexgol

Sales de Jujuy
Argentina

 | 

2023
Instalación de Tubería Pexgol para una Línea de Transporte de Salmuera Caliente.

Procesamiento de Salmuera de Potasa Caliente y Abrasiva

Compañía de Fertilizantes
Canada

 | 

2017
Transporte de agua de pozos

Transporte de Agua de Pozo a Alta Presión

Yamana Gold, Meridian Mine
Chile

 | 

2012