Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Mining Effluent Transportation in Cuba.

Estudo de Caso Nº

169

Cliente

Sherritt
Cuba

|

2020

Condições de Trabalho

Temperature: 90°C / 194°F | Flow Rate: 1,400-1,800 m³/h | Pressure: 4 bar | Fluid Components: Sand, mineral, sulfuric acid. 30-33% solids, pH 1.1 – 1.3, containing various metallic sulfates in solution along with solid-phase oxides, primarily iron oxide (d80 – 84 microns).

Solução Pexgol

Pexgol 630 mm (24″) class 12 & 10

Aplicação

Mining Effluent Transportation

Comprimento

6300 m / 20669.29 ft

Categorias

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

The Challenge

Sherritt, a global leader in nickel and cobalt mining and refining, faced the challenge of implementing an efficient and long-lasting system for transporting mining effluents at its Moa Nickel mine in Cuba. The project required a solution capable of transporting
1,400-1,800 m³/h of tailings at temperatures of 90°C and with a highly acidic pH (1.1 – 1.3), along with abrasive solids such as metal oxides and sulfates in solution.

The pipeline needed to cover a distance of 6.3 km from the processing plant to the tailings deposit, buried 2 meters underground in highly corrosive soil. Alternatives considered, such as stainless steel and fiberglass pipes, were deemed unfeasible due to their high costs. This prompted the search for a solution that balanced durability, chemical resistance, and ease of installation.

The Solution

Sherritt chose 630 mm (24”) Pexgol pipes in Class 12 and Class 10 due to their excellent resistance to chemicals, abrasion, and both external and internal corrosion. Key features that made Pexgol the ideal solution include:

  • Resistance to Extreme Conditions: The ability to handle highly acidic fluids, high temperatures, and abrasive solids without compromising the integrity of the pipes.
  • Ease of Handling and Installation: The lightweight material facilitated transportation and installation in complex terrain.
  • Long-Term Durability: Protection against external corrosion in aggressive soil conditions.

The installation was carried out using pipes supplied in 11.8-meter sections, connected through reinforced Series 1 electrofusion couplings. More than 500 welds were performed, all of which have shown optimal performance to date. To optimize time, three work teams were formed, each consisting of four trained operators, achieving a daily installation rate of 120 to 210 meters.

Estudos de Caso Relacionados

Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Improving the efficiency of salmon farming with the superior solution of Pexgol pipes.

Pexgol’s Pipe Solution Enhances Salmon Farming

Mowi
Chile

 | 

2021
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017
Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022