Skip to content

Gas Wells: Formation Water Treatment

Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Estudo de Caso Nº

64

Cliente

Canacol
Colombia

|

2018

Condições de Trabalho

Water with gas and minerals | Pressure: 15 bar | Temperature: 20°C

Solução Pexgol

Pexgol 160 mm (6”), Class 15

Aplicação

Formation water transportation

Comprimento

11 Km

Categorias

Installation of Pexgol pipes for the transport of formation water (gas and minerals)

The Challenge

Canacol together with the engineering company A.B. Projects had the mission of creating new wells for gas extraction and transporting it for distribution in Cordoba, Colombia.
Due to the high pressure for the gas transportation (above 100 bar) the client used Flexsteel (flexible pipes made of layers of polyethylene and steel). Additionally, at the exit of the wells, the gas had to be separated from the water that was underground through a turbine. But the separated water still contained traces of gas and minerals that needed to be treated once again.

Pexgol Solution

Canacol and A.B. wanted to use a reliable pipe to carry out the separation of water from surplus gases and minerals, but having used the Flexsteel pipe would have incurred on excessive expenses. Therefore they selected Pexgol thanks to its possibility of supply in long lengths, its high levels of safety and its low installation cost (versus other materials for high and low pressures).

The 11 km of pipe were installed in just one week: the uncoiling and laying of the pipes took 3 days and then the joints were connected by electrofusion and the pipes buried.

Pexgol proved once again to be an excellent solution for oil or gas wells where it is required to transport water for treatment with pressures that are below 30 bar.

Estudos de Caso Relacionados

Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013