Transport of Muddy Water in a Palm Oil Processing Plant

Transport of Muddy Water (Pome) witha High Content of Organic Load.

Estudo de Caso Nº

85

Cliente

La Gloria
Colombia

|

2020

Condições de Trabalho

Temperature: 80°C | Flow: 36m³/h

Solução Pexgol

Pexgol 110 mm (4″), clase 12

Aplicação

Muddy water transportation

Comprimento

1200 m

Categorias

Transport of Muddy Water (Pome) witha High Content of Organic Load.

The Challenge

La Gloria, a company dedicated to the extraction of palm oil in César (Colombia), required a new line to transport muddy water to the oxidation ponds. From the florentino lagoon (treatment pool), passing through the main road and the plantation, the excavation and installation of the pipe had to be carried out in the crop, between palms without causing damage to the plants and the irrigation pipe. In addition, given the operating conditions and the type of fluid, a pipe was required that resists high temperatures and has a low internal roughness index due to incrustations.

Pexgol Solution

Due to the high costs of carbon steel pipe, added to the cost of assembly, it was decided to use Pexgol pipes.

Pexgol was selected for its quick and easy installation, fewer joints and the possibility of supplying it in rolls.

The installation of the 1200 meters was carried out in 4 hours. Four electrofusion joints were used for the splicing of the sections and a mechanical joint was used at each end.

Estudos de Caso Relacionados

The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Pexgol enabled a safe and efficient installation across a highly constrained refinery layout.

Nitrogen Transport in a Complex Industrial Environment

YPF
Argentina

 | 

2025