Industrial Waste Water to MBR Treatment Facility

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Estudo de Caso Nº

103

Cliente

Chip Manufacturer
Israel

|

2021

Condições de Trabalho

Design temperature: 50ºC | Pressure: 4 bar

Solução Pexgol

Pexgol 400 mm (16”), class 10

Aplicação

Industrial treated water transportation

Comprimento

1000 m / 3281 ft

Categorias

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to replace an 10” HDPE line that transported industrial waste water to an MBR treatment facility.

Pexgol Solution

Having seen Pexgol’s experience in other projects in Israel and around the world, the client decided to install a 1000 meter Pexgol 400 mm, class 10 pipe.

The client was able to install the entire system in only 20 days since the pipes were supplied in sections of up to 57 m. Furthermore, Pexgol pipes do not require expansion loops since the pipe is able to withstand contractions and elongations without deformation.

Using Pexgol pipes allowed a faster installation time, helping reduce the total cost of the project.
It minimized potential failure points. Also reducing the cost of connections along the line.

The installation was done on pipe-racks of 8.5 meter above ground. The connections were made using electrofusion welding and flanges. Additional fittings such as PE-X elbows and others were used.

Estudos de Caso Relacionados

Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016
Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022